Plot plans are generally developed in stages, from the initial concept to the ftilly dimensioned document at the construction issue stage. [Pg.28]

The proposal plot plan, shown in Exhibit 3-1, is developed during the estimate phase of the projea and is used to estimate bulk materials. It is also included in the proposal as a representation of the unit arrangement to the prospeaive client. The proposal plot plan is based on limited information and generally indicates only the principal items of equipment, main supporting facilities, and overall dimensions. [Pg.28]

After contraa award, the proposal plot plan is updated to suit the latest information and is reviewed and approved by the client. This document becomes the basis for the plant layout phase of the projea and is called the planning plot plan. A sample planning plot plan is shown in Exhibit 3-2. On completion of the plant layout phase—when all the equipment has been sized and is in the best position to suit the projea requirements and when all access roads, buildings, and pipe tacks have been located—the plot plan is finally issued for construction. Ihis is illustrated in Exhibit 3-3 as the construaion plot plan. [Pg.28]

To develop a plot plan, the designer must assemble the information discussed in the following sections. [Pg.28]

The equipment list This document lists all the items of equipment and buildings by number and description to be included within the unit battery limits. A sample equipment list is given in Exhibit 3-4. [Pg.29]


The survey requirements will depend on rig type and the extent of the planned development e. single exploration well or drilling jacket installation. Atypical survey area is some 4 km by 4 km centred on the planned location. Surveys may include... [Pg.43]

Increasing capacity of the existing institutions to plan, develop and implement technologically, environmentally and economically sound policy. [Pg.920]

Business and the Environment California Planning Development Report Environment Watch Latin America Environment Week... [Pg.129]

Is R D s role in the business understood Are technology plans developed and broadly understood Are R D resources organized in the best way to carry out its mission Is the organizational climate assessed Does the organization have measures for success Does the organization learn Audits in place ... [Pg.131]

After the preceding considerations have been taken into account, a test plan is developed to best meet the goals of the program. This might involve one of the standard plans developed by statisticians. Such plans are described in various texts (Table 1) and are considered only briefly here. Sometimes, combinations of plans are encountered, such as a factorial experiment conducted in blocks or a central composite design using a fractional factorial base. [Pg.522]

Master plan development for PTPM. A master plan must be created. Total condition monitoring equipment should be designed, and equipment should be purchased. [Pg.729]

When using the defect-detection approach to quality control certain problems develop. Inspection does nothing to improve the process and is not very good at sorting good-from-bad. Also, sampling plans developed to support an acceptable quality level (AQL) of 5%, for example, say that a company is content to deliver or reject 5% defects. [Pg.333]

More involvement of the mentor in planning development assignments for the mentee. [Pg.97]

Another external response to concerns about MCOs has been an increased interest in measuring the quality of care they deliver [35]. This interest has resulted in the development of numerous quality indicators. One example, HEDIS (Health Plan Employer Data and Information Set), is a standardized set of performance indicators used to compare health plans. Developed by the National Committee for Quality Assurance, HEDIS measures allow employers and employees to evaluate different plans. Only a small number of HEDIS indicators are related to medication use, but more drug-related indicators are likely to be added in the future. The use of quality indicators likely will increase as the measures become more refined and tested. [Pg.805]

The plan must be coordinated with local emergency response plans developed by Local Emergency Planning Committees (LEPCs) and local emergency response agencies. As with similar OSHA regulations, the Resource Conservation and Recovery Act (RCRA), and the... [Pg.73]

The continuing care plan, developed prior to discharge from treatment into aftercare, is constructed with the different spheres and zones of recovery in mind. The ultimate goal of the continuing care plan is to help the client move into this new phase of recovery as seamlessly as possible. So, like the treatment plan (remember Chapter 4), the continuing care plan should be comprehensive but not overly intrusive, should be simple enough to follow, and should be developed collaboratively with the client prior to discharge. [Pg.237]

The first stage of the site characterization process is the customization of the generic plan developed as part of planning and preparation for responding to contamination threats. In general, the incident commander will develop the customized plan in conjunction with the site characterization team leader. The steps involved in the development of the plan include (1) perform an initial evaluation of information about the threat, (2) identify one or more investigation sites, (3) assess potential site hazards, (4) develop a sampling approach, and (5) assemble a site characterization team. [Pg.114]

The practice of brand plan development and its NCE forecast component is designed to leverage knowledge from a cross-functional team, and in a certain sense it does. But because the traditional forecasting process is fundamentally disconnected from the operational realities of the disease marketplace, the marketer/brand manager lacks a tool to quantitatively analyze the effects of the product strategies developed. In other words. [Pg.625]

Together, the defined/written series of tasks, test methods, requirements and docnmentation required to carry out the validation procedure for a system can be described as the validation protocol. The instrnc-tion mannal for all of this is the validation plan, developed by the validation team. [Pg.305]

The Commander of the Chemical Corps Research and Engineering Command, die Chief Chemical Officer, and the Surgeon General forwarded a plan developed by die Chemical Corps, listing seven investi tive studies in progress. After its approval, ftiey downgraded the original Secretary of Defense s memorandum to Confidential. ... [Pg.248]


See other pages where Plan development is mentioned: [Pg.17]    [Pg.87]    [Pg.187]    [Pg.187]    [Pg.193]    [Pg.67]    [Pg.151]    [Pg.59]    [Pg.365]    [Pg.818]    [Pg.66]    [Pg.189]    [Pg.34]    [Pg.597]    [Pg.73]    [Pg.76]    [Pg.145]    [Pg.12]    [Pg.189]    [Pg.223]    [Pg.70]   
See also in sourсe #XX -- [ Pg.95 ]

See also in sourсe #XX -- [ Pg.235 , Pg.242 ]




SEARCH



Action plan for sustainable development

Assessment, sustainable development planning

Biologies clinical development plan

Business operation plan, development

Care plan development

Clinical development plan

Clinical development plan communication

Clinical development plan costs

Clinical development plan data management

Clinical development plan dosage form

Clinical development plan drug interactions

Clinical development plan executing

Clinical development plan patient numbers

Clinical development plan process improvement

Clinical development plan quality assurance

Clinical development plan quality control

Clinical development plan technology

Clinical development plan training

Communication program plan development

Design and Development Planning

Design and development plans

Design team implementation plan developed

Design/development plan

Develop Company Goals and Get Everyone on Board with the Plan

Develop a Program Plan

Develop a Resource Plan

Developing a Crisis Communication Plan

Development Assurance process validation planning

Development Assurance process verification planning

Development of a Long-Term Maintenance Plan

Development of an Emergency Response Plan

Development planning

Development planning

Dioxin plan development

Drug development project planning

Emergency response plan procedures development

England Rural Development Plan

Evidence investigation plan development

Exploratory development planning

Facility planning development process

Field development planning

Fire plan, development

Full development detailed plan

Full development plan execution

GEMIs Approach to Sustainable Development Planning

Generally program plan development

Generally resource plan development

Good clinical practice development plan

Hazard communication plan developing/implementing

Human resources program plan development

Implementation case study plan development

Intervention plan development

Local Plan Development

Long-term planning development

Patient Safety Plan Development Considerations

Personal development plans

Plan development General Section

Plan development budget

Plan development elements

Plan development examples

Plan development facilities

Plan development generally

Plan development hybrid" approach

Plan development management style

Plan development program creation

Plan development schedule

Plan development structure

Planning and Development Methodology

Planning and Managing Product Development

Planning for the Development of a Fertilizer Industry

Planning in development

Planning the Method Development

Planning, Development, and Testing of Catalysts

Plot plans development

Principal elements in developing a workplace health and safety plan

Procedure development emergency response plan procedures

Product development plan

Program designing plan, development

Project Plan Development

Project planning development

Relapse prevention plans, developing

Safety Plan Development Considerations

Software Development Plan

Specifications plot plan development

Spiral development action plan

Staff training plan, develop/management

Step 4 Develop a high-level intervention plan for phase II

Strategic planning development

The Need for Developing a Plan

© 2024 chempedia.info