Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Project task dependencies

The size of the project team depends on the particular tasks that are to be performed and the hazards that may be encountered. Keep in mind that a wide variety of disciplines may not be required for every project. During the early stages of planning, an organizational chart should be developed. This chart can serve to visually depict the following ... [Pg.31]

The third question to be answered is What can be done concurrently Although this question implies that we would be doing more than one activity at the same time, this is not necessarily true. What we really mean is that both tasks depend on the completion of the same operation. Concurrently indicates a common need for prior work. Start all diagrams with an arrow marked lead-time and show all actual work starting after it. (Lead-time - preparation time to undertake a project.)... [Pg.823]

Whether you choose to free up time for a new project will depend very much on what you regard as legitimate and proper behaviour for yourself. If you believe that your real job Is to stay on top of the routines and do the necessary firefighting, then you are likely to have an equivocal attitude towards any task that takes you away from this. On the other hand, if you believe that as well as keeping the show on the road, peut of your real job is to do with putting on new shows or new acts, then you are likely to be motivated to find the time for both. [Pg.174]

The dependencies of the displayed project tasks are as follows Tasks 1 and 2 may start at the same time Task 1 must be finished before Task 3 can commence Task 4 cannot start before Task 2 and part of Task 3 (5096) have been accomplished Tasks 3 and 4 must be finished before Task 5 commences. The logic of this model project allows Tasks 2 and 4 some extra time alternatively these tasks may start later. [Pg.21]

Main project tasks should only be considered as completed when their objective has been achieved. As a control instrument, these objectives must be included in the project plan and must be defined in a measurable way. Figure 2 depicts these only as a symbol ( ) followed by the reference number as given in Figure 1 to maintain the clarity of the example. Because of their importance, the main objectives may be accentuated and shown with their descriptions. They indicate the assumptions on which the rest of the plan is dependent. They also serve... [Pg.22]

As described above, the backbone of the plan is basically established starting at the end of the project, then working through to the beginning. To sequence the different task sections correctly it is necessary to check backwards and forward to see how the different tasks depend on each other. [Pg.23]

Two major conflicts in terms of task dependencies between project sections remain in the example of Figure 2 (upper half) after a first arrangement of the different tasks within each of the four sections. In order to get an antigen which is immunogenic in mice and rabbits (see 11/1) at least some immunization experiments with Antigen X (task... [Pg.23]

If one wants to plan and control a larger project in a serious manner, project management software packages are essential and save a lot of time. These programs use entry data such as task descriptions, their duration, start or finish times, tasks dependencies and milestones to automatically sequence and schedule the project tasks. Conflicts and logic errors are identified and the project is re-scheduled after these have been corrected. A critical path analysis function reveals and... [Pg.29]

PERT (Performance Evaluation Review, and Tracking) and CPM (Critical Path Method) charts (flowcharts) show the flow, connectivity, and interdependency of project tasks, activities, and goals. A PERT chart (Figure 27.9) depicts the activities in the order that they will need to be carried out, either in series or in parallel. These charts also identify which activities need to be completed (or initiated) before the next activity, which is dependent on it, can be initiated. [Pg.432]

When the task and deliverables list is complete, the logical order in which tasks should be performed is defined. This is done by first determining task dependencies at the lowest level of the work breakdown structure. These dependency relationships can be portrayed in the form of a project network diagram. An example of task dependencies is shown in Figure 3. [Pg.1339]

The EDF/Sogin Consortium believes that the assistance provided through K1.01/98A project complies with the Tacis project TOR as a whole. The achievements of each project task will be less or more valuable for the elaboration of the decommissioning plan depending, among others, on the relevance given by the Kazakhstan side on various items of the plan. [Pg.157]

A. Consider the following project tasks and their interrelationships a) A is the initial task b) E and F can be performed simultaneously and cannot be started before B is completed c) I depends on F, G, and H d) K can begin only after E and I are finished e) L must follow J and K f) J cannot start until E is completed g) C must be completed before G can begin h) B, C, and D caimot begin until A is completed and can be performed simultaneously i) D must be completed before H can begin and j) L is the final task. [Pg.228]

These instruments are designed to perform specific analytical tasks. Depending on the capabilities of such instruments, their use and operation may be scheduled in a communal setting without problems however, if frequent use or a long-term project is planned, arrange-... [Pg.72]

Depending on the product and sales arrangement, the revenues calculation can take from a few man-hours to many man-months of effort. For instance, determining the price for a synthetic fuel from coal can be done in a very short time, based on the cost of service. However, if the price is tied to the price of natural gas or oil, the task becomes very difficult, if not impossible. On the other hand, determining the sales growth and selling price for a new product requires a great deal of analysis, speculation, market research, and luck, but projections can be made. [Pg.240]

A project produces a subset of models and diagrams that describe the design. For some projects, the order in which these are produced will be mostly top-down for others, more bottom-up. In almost all cases there are multiple development tasks that can proceed in parallel depending on project resources and constraints. In all cases, the relationships among the artifacts are the same, and the most important initial methodology question for any project to answer is... [Pg.544]

A project development team completes a multitude of tasks over the project lifetime. Some tasks are heavily dependent on others and should be serialized, perhaps using Pattern 13.3, Short-Cycle Development others are largely independent and should proceed in parallel because downstream work is dependent on them. [Pg.562]

At Los Alamos National Laboratory in New Mexico the Analytical Chemistry Group (C-AAC) supports the Pu-238 Heat Source Project that fabricates heat sources for use in the space industry. These heat sources have been used on NASA s deep-space probes and on instruments exploring the surface of Mars. The chemical and isotopic purity of the heat sources are critically controlled to ensure dependable service. The Radiochemistry Task Area performs analyses of the heat source material for four radioisotopes americium-241, plutonium-238, neptunium-237, and uranium-235. [Pg.314]

The students used the Gantt chart to plan and monitor the project progress. Each team prepared a detailed list of tasks, milestones and deliverables. A timeline was constructed based on the completion time, delivery schedule and estimated time needed to complete each tasks. The Gantt chart enabled the students to identify dependency between various tasks and recognize potential bottlenecks in the project. The critical tasks, scheduled tasks, completion dates and delivery time were clearly labeled. Each week the teams met to discuss and update the Gantt chart, as old tasks were completed and new one started. [Pg.356]

The hippocampus has innumerable afferent and efferent connections to other brain structures both within the limbic system and beyond. There are receptors for many different chemical signals ranging from the "classical neurotransmitters such as acetylcholine to steroid hormones and neurotrophic factors. Some of these receptors are located in the synapses that form the intrinsic hippocampal circuits and others are the targets of specific projection pathways from other brain areas. A comprehensive review of all neurotransmitter interactions relevant to function is not within the scope of this chapter. There are detailed reviews of modulation of neurochemical systems on place learning in the watermaze (McNamara and Skelton, 1993) or other limbic-system dependent tasks (Izquierdo and Medina, 1995) in animals. The effects of key neurochemical, other than NMDA channel-mediated, and environmental influences are discussed below. [Pg.75]

Other freezeWALL projects are similar in namre and had costs between 400,000 and 10 million depending on the size and complexity of the task (D19593B). [Pg.599]

The link between PAC and visuospatial attention has been confirmed by recordings in monkeys (Robinson et ah, 1995). Neurons in PAC area 7a increased their firing, depending on whether the animal attended to the region of space where the stimulus occurred. Parietal neurons exhibit a variety of complex, attention-related responses in monkeys performing the Posner task. Neurons in area 7a also appear to create world-referenced maps of visual space, and they project this information to the dorsolateral PFC, which uses this information to effectively guide behavior. [Pg.100]


See other pages where Project task dependencies is mentioned: [Pg.460]    [Pg.190]    [Pg.714]    [Pg.302]    [Pg.210]    [Pg.371]    [Pg.935]    [Pg.158]    [Pg.234]    [Pg.86]    [Pg.377]    [Pg.97]    [Pg.241]    [Pg.85]    [Pg.123]    [Pg.129]    [Pg.189]    [Pg.708]    [Pg.332]    [Pg.212]    [Pg.495]    [Pg.256]    [Pg.258]    [Pg.10]    [Pg.32]    [Pg.547]    [Pg.215]    [Pg.62]    [Pg.8]    [Pg.101]   
See also in sourсe #XX -- [ Pg.17 , Pg.20 , Pg.21 , Pg.22 , Pg.28 , Pg.29 ]




SEARCH



Dependency, task

Project dependencies

Tasks

© 2024 chempedia.info