Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Milestones plans

Under the VATIP, each participating mill develops Milestones Plans for each fiber line that it enrolls in the program. Permit writers will use the Milestones Plan to incorporate enforceable... [Pg.886]

Why is it so difficult to muster just the right amount of perseverance in a corporate environment We believe perseverance is foremost a decision-making problem. To meet performance criteria, project management needs discipline. Typically, at the start of a project the project leader develops a milestone plan as guidance for future project evaluations. When milestones are not met after the originally estimated time, management typically decides to withhold further funding because it has lost faith in the project s likelihood of success. [Pg.168]

Unfortunately, in many milestone plans, especially in research, we see huge overconfidence in the original estimate of time requirements. This initial overconfidence can be attributed to two factors time pressure and personal frame of reference. If the talk around the water cooler claims that no project with a total timeline of more than two years will be funded, no milestone plans longer than that will be submitted, even if more time is realistically necessary. If the typical time a bench scientist needs for promotion to a management role is five years on average, milestone plans will not extend beyond two to three years. Accordingly, if all research steps have to fit this short time span, project planners will decide to set shorter individual milestones than are actually required. Little wonder that projects are abandoned prematurely or project overruns compared to originally expected timelines are so common. [Pg.168]

An annual target-setting process for operational improvements needs to be established. Very specific targets have to be set for each plant and production unit, that in sum will allow the overall company target to be achieved. The process should start with a top-down target for cost savings, followed by bottom-up action and milestone plans. The improvement opportunities could be reductions in annual plant downtime to below ten percent per year as a sum of numerous measures derived from observations on the shop floor, i.e., reduction of downtime for specific vacuum pumps via preventive maintenance or substitution of a repairintensive pump by one more suited to the process step. [Pg.251]

Background to the PLC installation Organization and responsibilities Validation approach and the procedures to be used Results of any supplier selection process Ongoing operational requirements for GMP Ongoing operational requirements for lEC 61508 A milestone plan... [Pg.592]

Fig. 12.4 Milestone plans for easier and more complex projects (Kuster et al. 2008)... Fig. 12.4 Milestone plans for easier and more complex projects (Kuster et al. 2008)...
In addition to specific deadlines for each task and subtask, you should also consider program milestones, key pcrints in the plan at which you will want to review progress to date and make any necessary adjustments. For example, if you have adopted an element-by-element approach, you could consider completion of each PSM element as a milestone similarly, each facility s program would constitute a milestone, if that is the approach you ve chosen. [Pg.112]

What we have done. Outline installation roll-out plan schedule, responsibilities, milestones. [Pg.165]

Develop timetable for shutdown The management team should establish a macro-level schedule for the outage. Without complete planning, a definitive timeline can not be established, but the team should establish specific milestones that must be met. [Pg.820]

The alkaloid physostigmine found in the calabar bean is another classic milestone molecule in total synthesis. Metrics for thirteen plans to this molecule are summarized in Table 4.25. [Pg.159]

In the same way, consider the various documents of a development to be elements in a structure that you are editing (see Figure 6.44). The goal of the project is to fill in all the slots in the structure and make them all consistent when finished. Feel free to begin at the bottom, if appropriate, and don t worry if things get inconsistent en route provided that they come back in line at some planned milestone. [Pg.305]

The students used the Gantt chart to plan and monitor the project progress. Each team prepared a detailed list of tasks, milestones and deliverables. A timeline was constructed based on the completion time, delivery schedule and estimated time needed to complete each tasks. The Gantt chart enabled the students to identify dependency between various tasks and recognize potential bottlenecks in the project. The critical tasks, scheduled tasks, completion dates and delivery time were clearly labeled. Each week the teams met to discuss and update the Gantt chart, as old tasks were completed and new one started. [Pg.356]

The reports shall include engineering, purchasing, manufacturing, and testing schedules for all major components. Planned and actual dates and the percentage completed shall be indicated for each milestone in the schedule. [Pg.164]

The ED plan should lead to one or more decision milestones at which an agreed body of information will be provided in a defined time. The plan may consist of as few as one or two studies in healthy volunteers, which will deliver in 6-9 months, or it may involve a complex series of studies in healthy volunteers and patients, which might take 2 years. Whatever is appropriate, the information available at the decision milestones should enable the company to compare the actual profile with the previously agreed MAP. The company will then be in a position to make a well-founded decision on whether to continue development with a much reduced risk of failure or whether to stop and concentrate precious resources elsewhere. [Pg.147]

An overview of the project plan, with timeline and delineated critical path, may be conveniently presented as a Gantt chart. A decision tree is another visual aid which can serve to clarify the critical information required for each milestone decision. [Pg.147]

As with any plan, well-defined milestones and checkpoints must be incorporated and subsequent activity should not proceed until these have been achieved. The plan must always be sufficiently detailed to identify supporting activities, such as toxicological studies, that must be completed to allow development to continue without interruption. Many of these activities can, and should, run in parallel. [Pg.319]

The project validation plan is a live document that should be reviewed against each life-cycle step and any other validation milestones (as a minimum). Any changes to the plan should be identified on a revision history section within the document. The plan should be retained in the validation file and should be easily accessible. [Pg.581]

During the design, specify and procure stage, preliminary process control and implementation plans are developed. These plans lay out the basic timing/milestones for each effort, as well as define the roles necessary to complete all the given tasks. It is expected... [Pg.23]

Needless to say, these were stretch targets. Nevertheless, in four months, the project teams came up with 430 projects that made it possible to meet the aspiration. A total of 45 of these projects were A projects, which were to deliver 60 percent of the improvement. Implementation plans for A projects were very detailed with clear activities and milestones, as well as monthly resource plans and impact by activity. For the less important B and C projects, there were simpler planning requirements. [Pg.351]

The next step in the business planning process is to define major milestones and an action plan of implementation and operation of the program. This action plan should detail the start and finish dates and list responsible individual(s) for each task necessary to accomplish the objectives of the business plan. The action plan should include periodic monitoring and assessment of the performance (i.e., clinical, financial, or other) of... [Pg.55]


See other pages where Milestones plans is mentioned: [Pg.887]    [Pg.150]    [Pg.887]    [Pg.150]    [Pg.133]    [Pg.239]    [Pg.397]    [Pg.78]    [Pg.181]    [Pg.366]    [Pg.156]    [Pg.34]    [Pg.260]    [Pg.621]    [Pg.26]    [Pg.327]    [Pg.112]    [Pg.170]    [Pg.133]    [Pg.256]    [Pg.284]    [Pg.226]    [Pg.864]    [Pg.176]    [Pg.38]    [Pg.38]    [Pg.60]    [Pg.60]   
See also in sourсe #XX -- [ Pg.886 ]




SEARCH



Milestone

Milestoning

Project planning milestone charts

© 2024 chempedia.info