Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Responsibilities contractors

Both histamine and 5-HT have been demonstrated in extracts 5-HT is responsible for some of the bronchoconstrictor activity of cotton dust extracts. Brom-lysergic acid, a specific 5-HT inhibitor, partially reduces activity, suggesting the presence of an "unknown contractor." This does not appear to be acetylcholine or bradykinin. Thus, although histamine, 5-HT, and the "unknown contractor" can cause immediate contractor responses, delayed onset contractions may still be due to secondary release of histamine (105). [Pg.155]

Finding 6. The loss of experienced personnel prior to completion of closure could jeopardize the cost-effective and safe implementation of closure plans. Fostering personnel retention during facility closure could present a challenge, particularly if the contractor responsible for closure is different from the one responsible for operations. [Pg.24]

On Scene Commander (OSC) The overall coordinator of an oil spill response team, usually a representative of an oil company, a government official, or an independent oil spill cleanup contractor responsible for on-site strategical decisions and actions throughout each phase of a cleanup operation and who maintains close liaison with the appropriate government agencies to obtain support and provide progress reports on each phase of the emergency response. [Pg.248]

The project at Plant Sweatt was organized with Southern Company Services as EPRI s prime contractor responsible for project management, project direction and subcontractor performance. Subcontracted to Southern Company Services were Babcock Wilcox (B W) and KVB. B W provided technical consultation and boiler performance evaluations, KVB provided combustion gas emission characterizations and supplementary technical consultation. [Pg.140]

Space for contractor responses to be included in body of report... [Pg.845]

An independent contractor responsible to the construction manager or owner should do testing and balancing (TAB) of mechanical systems. All start-up should be complete and initial valve or damper settings made (and recorded) by the subcontractor before testing and balancing begins. The TAB contractor should not have to repair equipment or troubleshoot inoperative equipment but rather only adjust and verify performance of equipment. [Pg.206]

The contract for ozonation equipment placed upon the contractor responsibility for operating the ozone-generating plant for 90 days, during which time he was to... [Pg.437]

Contractors responsibilities. Obligations, for example, to treat patients according to accepted ethical standards and to accept the consequences of medical negligence. [Pg.80]

The health and safety regulations make the main contractor responsible for the health, safety and welfare of all workers on the construction site. The main contractor must put in place a health and safety policy for each construction site and provide guardrails, working platforms, lighting, toilets, hand-washing facilities, first aid and site accommodation. There is also a duty to wear head protection on-site, including electricians. [Pg.332]

OSHA has cited two contractors responsible for the rehabilitation and painting of a municipal water tower in New Hampshire for alleged violations of safety standards following the death of a worker who fell 90 feet from the tower. [Pg.339]

Contractor Management Employers must establish details relating to use of contractors for repair, maintenance, and other support for a process. There must be a clear explanation of contractor responsibilities. Employers must share information about hazards of the process. [Pg.353]

Section 10 CFR 830.205 of fhe Nuclear Safety Management rule, requires DOE contractors responsible for Cafegory 1, 2, or 3 DOE nuclear facilities develop TSRs. These TSRs identify the limitations to each government-owned contractor-operated (GOCO) nuclear facility based on the DSA and any additional safety requirements established for the facility. Although not required by the Rule 830, there also may be a need to establish TSRs for the safe operation of radiological facilities (DOE Order 5480.22). [Pg.665]

Title 10 CFR 830, Subpart B—Safety Basis Requirements—requires the contractor responsible for a DOE nuclear facility to analyze the facility, the work to be performed, and the associated hazards and to identify the conditions, safe boundaries, and hazard controls necessary to protect workers, the public, and the environment from adverse consequences (DOEG 421.1-2). These analyses and hazard controls constitute the safety basis on which the contractor and DOE rely to conclude that the facility can be operated safely. [Pg.669]

Construction contractors, responsible for executing the plans developed by the architect, mechanical engineer, and structural engineer. [Pg.2363]

Other outside contractors, responsible for certain speciahzed custom items which can not be developed or fabricated internally or by any of the other contractors. [Pg.2363]

The Construction (Design and Management) (CDM) Regulations require the installation designer to cooperate with other designers, such as the architect, the planning supervisor and chent, to ensure that the installation will be safe both initially and subsequently as it is altered to suit the various phases of the construction work. This entails a consideration of the risks and a determination of the means to be used to minimise them. When the site work begins, the electrical contractor responsible for the temporary installation has to plan his work so that it can be done safely. [Pg.181]

All surfaces affected by the work shall be restored to their pre-construction conditions. Performance criteria for restoration work are to be similar to these employed in traditional open excavation work Performance specifications should be developed as to hold the contractor responsible for settlement/heave damage that may occur along the drill path... [Pg.178]

The importance of contract fonn needs to be appreciated whether a project is predominantly in-housc with perhaps relatively small involvement of subcontractors, or the entire work is to be entrusted to a contractor. Responsibility for commissioning needs to be dearly defined to avoid ambiguities at a later stage. [Pg.3]

Some facilities prefer to provide a safety orientation to each and every contractor and subcontractor employee as a condition of gaining access to the facility to ensure that the orientation is rigorous and to ensure that there is documentation of the orientation and that each person understood the content. If safety orientation is a contractor responsibility, the program should include an acknowledgment by the contractor that appropriate site safety training will be provided to all contractor employees and subcontractor employees before work begins on the premises as well as the transmittal of documentation that the orientations were conducted and understood. [Pg.59]

SRSPO procedures shall clearly define line responsibilities for identifying and pursuing problems at the SR reactors. In addition, the procedures shall clearly state actions to be taken if contractor response is inadequate for the situation. [Pg.10]


See other pages where Responsibilities contractors is mentioned: [Pg.203]    [Pg.38]    [Pg.158]    [Pg.62]    [Pg.62]    [Pg.235]    [Pg.42]    [Pg.151]    [Pg.6]    [Pg.125]    [Pg.457]    [Pg.76]    [Pg.40]    [Pg.315]    [Pg.286]    [Pg.10]    [Pg.124]    [Pg.125]    [Pg.125]   
See also in sourсe #XX -- [ Pg.207 ]




SEARCH



Contractors

Reporting contractor responsibilities

© 2024 chempedia.info