Procurement component

In case a new plant is to be erected and operated, it has to be verified at first if an authority approval will be required and if so, based on which law /4.9/. The statutory regulations and conditions may vary considerably subject to the respective country. In highly developed industrial nations the statutory regulations are usually very complex /4.10/. [Pg.103]

Therefore, a universal depiction of the activities required for the approval planning is not possible. It is advisable to contact the relevant authorities of the respective country in due time. In general, it is also possible to commission engineering agencies or a lawyer s office specializing in the field of authority engineering. [Pg.103]

The components of a designed plant can be derived from the components list AH main abrogates such as vessels, pumps, compressors, heat exchanger, reactors, rectifications columns, centrifuges, agitators etc. with more or less detailed specifications are listed. The components list is already being prepared within the framework of the basic engineering and has to be completed, amended or extended, if required. [Pg.103]

A similar situation appUes to technical data sheets of the components the technical data sheets of the basic engineering have to be examined and completed. [Pg.103]

Moreover, the quotations for the preliminary inquiries from the planning phase are available. In case the prehminary inquiries have been spread wide enough (i.e. more than five inquiries to subcontractors) the execution should be concentrated on not more than three potential subcontractors. This process bears the advantage that the usually extensive documentation for the main inquiry does not need to be copied and dispatched so often. In this connection it has to be considered that, for example, all customer specifications having to do with the respective type of [Pg.103]


Bharadwaj, N. 2004. Investigating the decision criteria used in electronic components procurement. Industrial Marketing Management. 33(4) 317-323. [Pg.358]

Imagine only one single purchased part cannot be procured on time for a customer order (Fig. 30). All other components procured for this order must then wait. [Pg.85]

These detail time schedules are subordinated to so-called framework time scheduling. Framework time scheduhng contains only the essential, i.e. contractually stipulated or penalty-related basic dates, as well as the beginning and the end of the project sections. Figures 4.3, 4.4 and 4.5 show examples of a framework time schedule, a time schedule for component procurement and for the commissioning. [Pg.97]

Figure 4.4 Example of a time schedule for component procurement. Figure 4.4 Example of a time schedule for component procurement.
With the component procurement, however, the actual ordering process is not completed. Similar to the operator who seconds an engineer for the monitoring of the project development, the plant manufacturer will control the activities of his or her subcontractors. The main motive for this so-called expediting is the avoidance of delays in delivery. The consequences of a subcontractor s delay in delivery will be excessively high costs. The intensity of these expediting efforts depends on the company s philosophy or the cost-value-ratio. [Pg.108]

The multitude of possible aspects which have to be considered in the component procurement process is almost incalculable. However, in order to point up the further approach, layout and procurement of components should be set out in more detail with the help of the recurring examples of vessels and pumps . [Pg.109]

In the next step, so-called piping alignments are planned, which are the main routes of the pipes. The individual pipes, as already explained in section 4.2, Component procurement , are led directly into the pipeline routes, then within the route they are running parallel to the other pipelines and leave the pipeline route only shortly before the connecting point. [Pg.156]

The quality documentation of the subcontractors emanates from the quality assurance plans (see section 4.3, Component procurement ). Furthermore test certificates, test protocols etc. of the quality-related activities carried out on the building site during the assembly and start-up, such as weld inspections, acceptance of the Technical Control Board etc., have to be enclosed. [Pg.165]

To illustrate how the profits may be computed, we consider a simple case where finished products are sold only in the EE. Thus, consideration of duty draw-back and demand in ME are not included in this analysis. Note that if the total quantity produced is 2, a fraction of it will be produced using components procured from EE (= < ) The remainder is produced using components procured from ME (= q ). Assuming we can specify the distributions of ye and ym the total amount of components delivered for assembling Q would equal Ye1e + Ym<1m = Q Q is clearly a random variable. The manufacturer s expected sales will be Ey Ed [Min YE E +and, therefore, his expected profit is expressed as... [Pg.218]

Assuming unit procurement costs of Ce and Cm, and unit assembly cost of c, the component procurement cost is expressed as CEqEEy Ys + MqmEy YM-Next, note that the expected number of units assembled is expressed as... [Pg.231]

FMS providers handle most of the component procurement for their customers. More than 95 percent of the procurement is turnkey, meaning that the EMS provider sends out the purchase order for parts. Given the commonality of parts in the electronics industry, EMS providers could get lower prices for customers (especially compared with smaller OEMs) because of their large spending on parts. Flextronics, for example, was spending well over 10 billion a year on parts, allowing it to get good deals from suppliers. [Pg.442]

Control over procurement of raw material and components that compose inputs... [Pg.249]

Procurement policy - how the organization will obtain the components and services needed... [Pg.90]

The Seminar System Implementations may be complete in the sense that every required action is dealt with, but what we see in the diagram are specifications of the components. We can t really take our money and go home until we ve procured or made an implementation for each one. [Pg.53]

Note. All of the RDX component and portions of the TNT and wax are added as Composition B. A separate calcium chloride determination need only be 9one if required in the contract or order (See 6.2). Percentage requirement of Calcium Chloride is 0.5% 0.1% Calcium Silicate shall be determined as specified in 4.4.1.2 when used in the formulation of HBX compounds. The Calcium Silicate content shall be a minimum of 1.25 weight percent of the TNT content of the mixture and shall only be used in the HBX compositions when specified by the procuring agency (See 6.2). Calcium Silicate is designated for use only in Army formulations of HBX type explosive compositions. The major portion of the wax and all of the Nitrocellulose and lecithin are added as Composition D-2 ... [Pg.25]


See other pages where Procurement component is mentioned: [Pg.111]    [Pg.87]    [Pg.103]    [Pg.103]    [Pg.103]    [Pg.103]    [Pg.105]    [Pg.107]    [Pg.109]    [Pg.109]    [Pg.111]    [Pg.113]    [Pg.115]    [Pg.111]    [Pg.87]    [Pg.103]    [Pg.103]    [Pg.103]    [Pg.103]    [Pg.105]    [Pg.107]    [Pg.109]    [Pg.109]    [Pg.111]    [Pg.113]    [Pg.115]    [Pg.163]    [Pg.21]    [Pg.79]    [Pg.442]    [Pg.64]    [Pg.67]    [Pg.210]    [Pg.118]    [Pg.146]    [Pg.264]    [Pg.203]    [Pg.350]    [Pg.20]    [Pg.4]    [Pg.241]    [Pg.121]    [Pg.172]    [Pg.51]    [Pg.29]    [Pg.22]    [Pg.26]    [Pg.565]   
See also in sourсe #XX -- [ Pg.87 ]