Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Plant design schedule

Figure 1.1 Sample of a process and plant-design schedule. Source Ref. 17, with permission. Figure 1.1 Sample of a process and plant-design schedule. Source Ref. 17, with permission.
The confluence of sharply rising Operations and Maintenance (O M) costs. NRC requested Individual Plant Examinations (IPEs) and increased personal computer capabilities gave rise to the R R Workstation. Its uses and maintains-current PSA models and databases for individual plants to perform O M planning and scheduling, and uses the PSA in IPE models to identify plant design, procedure and operational vulnerabilities. The Risk and Reliability Workstation Alliance was organized by EPRI to support the R R Workshop in order to achieve O M cost reduction, plant productivity and safety enhancement through risk-based, user-friendly, windowed software louls (Table 3.6 8). The Alliance, initiated in 1992, includes 25 U.S. utilities and four international partners from Spain, France, Korea, and Mexico. SAIC is the prime contractor for the R R Workstation, with participation of five other PSA vendors. [Pg.144]

The death of old products, the birth of new ones, changing demands, and the need to compose the optimal hierarchical production plan with an optimal use of the equipment and the shortest possible total production time make the timing of production more important than plant design. The use of rigorous optimization techniques can be most profitable at production planning and scheduling of existing batch plants, especially multipurpose plants. [Pg.506]

The above model consists of two main parts a scheduler and the plant to schedule. Since the scheduler defines exactly when to start and finish the tasks, the behavior of the entire system is deterministic. Running both parts, the scheduler and the plant, corresponds to a simulation in which one single behavior of the composed system is obtained. Obviously, this situation requires the presence of a scheduler which knows the (optimal) schedule. If such a scheduler is absent, then the resource automata in the plant receive no signals. Scheduling of a plant can be understood as the task of finding a scheduler automaton which provides the optimal schedule with respect to an optimization criterion. In the sequel it is assumed that a scheduler does not exist and the automata model is designed as shown in Figure 10.4. [Pg.224]

Design and Retrofit of Multiproduct Plants Design and Scheduling of Multipurpose Plants... [Pg.5]

A number of issues need to be resolved when dealing with batch reactors in industrial applications, ranging from design and planning of the plant to scheduling, optimization, and performance achievement of batch operations. Performance is usually specified in terms of productivity of the plant, safety of operations, and quality of final products. In order to meet such requirements, several problems need to be addressed ... [Pg.198]

Production planning studies the amounts of the various products which should be manufactured in a given plant when the production requirements are known. This problem must be considered during the plant design stage. Scheduling decides in which equipment each product should be manufactured, when the operation starts, and when it is expected to finish. [Pg.83]

A number of new solar power plants are under construction. In 2007, First Solar signed a contract to produce 685 mW of solar collectors over 5 years for 1.28 billion, or at a unit cost of 1.87/W. This might correspond to a 3/W installed cost. Southern California Edison is erecting a 500 mW plant designed by Solel Solar Systems of Beit Shemesh, Israel. It is scheduled to start up in 2009. [Pg.98]

Plant Site Scheduled Startup Design Capacity (Mbpd) F-T Unit Technology Investment Estimate/Daily Capacity Barrel ( /bbl)... [Pg.919]

Whatever the case of batch plants, either of multiproduct or multipurpose nature, few works have addressed the retrofit problem compared with the batch plant design problem. Most of the mathematical formulations used to model the retrofit problem usually lead to optimization-oriented problems. It must be also emphasized that scheduling is intrinsically associated with batch plant design/retrofit, and is part and parcel of the formulation of both issues. It can be considered as a sub-problem of the design/retrofit problem. As highlighted in the compared formulation of these companion problems, the retrofit problem appears to be a more constrained problem. Yet, the basic solution strategy involves the same mathematical approaches and tools. [Pg.230]

The plant design was carried out on an accelerated schedule. To simplify the construction, we opted to build the facility in phases. The first phase represents the core of the plant. It contains a pneumatic truck unloader coupled to a storage silo, a reactor tank and a Larox filter. This approach enabled us to start up quickly and to provide a good way to determine the compatibility of the washing plant with the rest of the facility. Phase 1 was completed in June 1999 and provided the capacity to wash up to 22,000 tons per year of oxide. [Pg.742]

A variance in quantity may reveal the extent of waste. For example, suppose a plant is scheduled to produce 22,700,000 kg for the coming year. Design calculations indicate that... [Pg.481]

However, unlike project work, studies are usually commenced without a definite plant design concept and construction plan these are subject to change, and the essential requirement is to find the most suitable concepts and plans which will become the basis for the detailed project designs, budgets, and schedules. Inevitably the plant design is developed in a series of iterations. Initially, relatively broad concepts are explored, and possible innovations are introduced. Some concepts, for example materials handling system, layout, or site location, may be quickly rejected, while others may need more detailed comparison to arrive at the best choice. The phases of initial conceptual development, and of more detailed design and evaluation, are often formally split into... [Pg.93]

By the nature of the process, it is apparent that there is no end to the amount of value engineering that can go into a plant design, given that time and resources are available. An engineer who finds himself contracted to fully value-engineer a plant design, within the ambit of a limited budget or schedule, may be in for a sticky time indeed. It is also... [Pg.118]


See other pages where Plant design schedule is mentioned: [Pg.640]    [Pg.475]    [Pg.554]    [Pg.13]    [Pg.663]    [Pg.57]    [Pg.77]    [Pg.23]    [Pg.26]    [Pg.110]    [Pg.178]    [Pg.406]    [Pg.14]    [Pg.18]    [Pg.440]    [Pg.465]    [Pg.19]    [Pg.2889]    [Pg.276]    [Pg.7]    [Pg.787]    [Pg.12]    [Pg.111]    [Pg.814]    [Pg.116]    [Pg.100]    [Pg.203]    [Pg.460]    [Pg.795]    [Pg.644]    [Pg.31]    [Pg.244]    [Pg.259]    [Pg.206]    [Pg.70]    [Pg.274]   
See also in sourсe #XX -- [ Pg.7 ]




SEARCH



Plant design

Schedule designation

Scheduling and Designing Multiproduct Plants

© 2024 chempedia.info