Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Validation operational qualification

The validation of ne v facilities, systems or equipment is usually accomplished using a four-stage process of design qualification (DQ), installation qualification (IQ), operational qualification (OQ) and performance qualification (PQ). [Pg.225]

Berg, T., Humphreys, P., Phillips, B. and Scherz, B., Recommendations on Validation Master Plan, Installation and Operational Qualification, Non-Sterile Process Validation, Cleaning Validation , PIC Publication PH 1/96. [Pg.520]

The validation process is subject to the following design specifications, user and performance requirements, preparation of a master plan/validation protocol (installation qualification, operational qualification, and performance qualification), execution of the protocol, preparation of a summary report, and on-going validation (and revalidation if changes are made). [Pg.1028]

In a GLP-compliant laboratory, a data system must meet explicit requirements guaranteeing the validity, quality, and security of the collected data. Operational qualification (OQ) must be performed after any new devices are installed in the laboratory system and whenever service or repair are performed. The role of OQ is to demonstrate that the instrument functions according to the operational specifications in its current laboratory environment. If environmental conditions are highly variable, OQ should be checked at the extremes in addition to normal ambient conditions. Performance qualification (PQ) must be performed following any new installation and whenever the configuration of the system has been changed. PQ demonstrates that the instrument performs according to the specifications appropriate for its routine use. [Pg.1038]

Validations fall into two types prospective and retrospective. In prospective validation (see flow chart in Figure 2) the validation is done in a sequential manner, involving installation qualification and operational qualification (IQ/OQ) of equipment (e.g., chromatography instrumentation or column hardware). Appropriate calibrations accompany the IQ/OQ. Process qualification, or PQ, involves formal review and approval of a PQ protocol, execution of this protocol, and issuance of a formal PQ report which includes data analysis and recommendations (i.e., approval/certification of the process). If the process is not approved, the report may recommend a redesign or redoing of the validation protocol and, in some cases, a return of the process to process development for further optimization. [Pg.118]

In following text an attempt is made to give an example of the types of documentation that must be prepared within the validation master plant for the installation qualification (IQ) and the operational qualification (OP). The examples given are restricted to the process and installation engineering aspects, and exclude the many other aspects, e. g. sterility, biological or chemical requirements, corporate policies or the production environment. The information described are organized in six categories ... [Pg.257]

Indeed, the need for capital investment in a CMO may not have been originally anticipated or planned for and may impact on the whole decision making process. Additional costs and time need to be set aside for training and equipment validation, e.g. PQ/IQ/OQ (process qualification/ installation qualification/ operational qualification), and if this includes equipment with radically different operating principles than currently available on site then additional costs will be required for equipment-specific operating personnel and training. [Pg.21]

This chapter defines the terms, responsibilities, requirements and recommended procedures involved in pre-installation, installation qualification (IQ), operational qualification (OQ) and performance qualification (PQ), which are all part of a typical HPLC system validation process. As the FDA does not publish a definitive reference or cookbook for these procedures, the suggestions herein are only recommendations. These have been successfully incorporated into formal standard operating procedures (SOPs) that have been implemented at a number of larger pharmaceutical establishments. As long as proper SOPs... [Pg.303]

As with any data generation or data-handling system, appropriate validation (instrument qualification (IQ)/operational qualification (OQ)/performance qualification (PQ)) is required to demonstrate that the system is accurately and reliably performing in accordance with the user-functional requirements. [Pg.390]

Instrument qualification or validation refers to the process of demonstrating an instrument s suitability for its intended use. The first step is to write protocols to cover the four main qualification elements design qualification, installation qualification, operational qualification, and performance qualification. Another qualification element, re-qualification, can be written as a separate protocol or included as part of the PQ protocol. These protocols must be performed in sequence. If the protocol meets its acceptance criteria, then the next protocol in the sequence can be executed. [Pg.57]

Apart from the qualification dossiers provided by vendors there seems, at present, to be very little information published on the performance of an operational qualification for capillary electrophoresis (CE) instruments other than a chapter in Analytical Method Validation and Instrument Performance. The chapter, written by Nichole E. Baryla of Eli Lilly Canada, Inc, discusses the various functions (injection, separation, and detection) within the instrument and provides guidance on the type of tests, including suggested acceptance criteria, that may be performed to ensure the correct working of the instrument. These include injection reproducibility and linearity, temperature and voltage stability, detector accuracy, linearity, and noise. [Pg.171]

Equipment validation comprises installation qualification, operational qualification, and performance qualification. The intention is to demonstrate that equipment is qualified for processing. [Pg.13]

The system consists of an oil-free compressor, drier, storage tank, and distribution system. The validation process consists of installation qualification, operational qualifications, and actual validation testing of the operational system. [Pg.219]

The documentation (installation qualification, operational qualification, etc.) established prior to initiating validation studies provides the foundation for the subsequent validation. A comprehensive steam sterilization protocol should include the following items ... [Pg.262]

The OQ phase of sterilizer validation shall consist of the development of an information package fulfilling the documentation requirements of the generic equipment operational qualification. The following sterilizer-specific documentation shall be incorporated in the operation qualification ... [Pg.279]

The lyophilizers are cleaned using a validated clean-in-place (CIP) cycle using hot WFI. After the cleaning process, a validated sterilization cycle is mn. The qualification of the steam sterilization cycle was performed during the operation qualification (OQ) of the lyophilizer. [Pg.491]

Steam sterilization validation. All autoclave operations conform to the Master Validation Plan employed at ABC Pharmaceutical Industries. The autoclave has undergone installation qualification, operational qualification, and performance qualification. The autoclave is revalidated on an annual basis. The equipment steam sterilization cycle revalidation data for the autoclave are provided in validated archives. [Pg.510]

When new equipment is purchased or there is a change in the manufacturing site, qualification exercises are performed as part of the validation process. Qualification (installation qualification, operation qualification, and performance qualification) for any equipment or facility is an extreme process which involves testing, verification, and documentation to assure that the particular equipment or facility is per the specification and meets the appropriate standards as defined by vendor and required by manufacturing and engineering personnel [14]. [Pg.92]

The terms instrument qualification and instrument validation are sometimes used indiscriminately. In this chapter, the term qualification refers to the site preparation and the testing employed to demonstrate that the instrument is properly installed in a suitable environment and the performance meets the predetermined specifications for its intended use. Qualification is a part of the whole validation life cycle. Validation refers to the process to provide assurance that the instrument is suitable for the intended application throughout the lifetime of the instrument. Installation qualification (IQ), operation qualification (OQ), and performance qualification (PQ) are performed to provide evidence that the user requirement specifications (URSs), functional requirement specifications (FRSs), and design qualification (DQs) have been met. The sequence of requirements setting and qualification events as well as the relationships between IQ, OQ, PQ and URS, FRS, and DQ are generally illustrated by the V diagram shown in Figure 2. Installation qualification demonstrates the fulfillment of the DQ. Similarly, OQ demonstrates the fulfillment of the functional requirements and PQ demonstrates the fulfillment of the user requirements. [Pg.798]

Equipment System Validation The GMP has special features regarding the equipment, setting several points for the validation, such as design qualification, installation qualification, operational qualification, and performance qualification. Each point must be given in a different document, so four documents must be generated for each equipment. Without any of these documents, the equipment cannot be considered adequate for GMP purposes. GMPs do not refer equipment validations nonetheless, they refer these four items, and therefore, equipment can only be considered validated after the approval of these four documents. [Pg.828]

Agilent Capillary Electrophoresis System Operational Qualification/Performance Validation, Agilent Technologies, Waldbronn, Germany, 2000. [Pg.195]

Equipment qualification covers the entire life of a product. It starts when somebody has an idea about a product and ends when the equipment is retired. For computer systems validation, this ends when all records on the computer system have been migrated and validated for accuracy and completeness on a new system. Because of the length of time and complexity, the process has been broken down into shorter phases design qualification (DQ), installation qualification (IQ), operational qualification (OQ), and performance qualification (PQ) [2]. The process is illustrated in Figure 17.1. [Pg.257]

Scale-up ensuring that installation qualification, operational qualification, performance qualification (IQ/OQ/PQ) activities are properly conducted These include cleaning validation, process validation, sterilization validation, and so forth, according to established corporate procedures. [Pg.35]

As noted, excipient manufacture should take place using qualified equipment and a validated process. Generally excipient equipment has been in place for many years so that classical methods of qualification, which is done as new equipment is commissioned, are inapplicable. To retrospectively qualify the installation, operation, and performance of equipment, it is suggested to rely on historical records. For installation and operation qualification, a protocol is prepared that illustrates how maintenance and production records will be used to support the hypothesis that the equipment was installed properly and is operating as intended. Then the protocol is executed by reviewing the maintenance and production records for the supporting data. Finally a report is prepared that includes the data from the records, which support the conclusion that the installation and operation of the equipment conforms to protocol requirements. It is suggested that maintenance and production records for a minimum of one year but preferably five years be reviewed. [Pg.380]

With the completion of the installation qualification, operation qualification and performance qualification, the equipment is considered qualified and process validation can proceed. A master validation plan should be developed that... [Pg.381]

Installation and operational qualification work includes verification of temperature, pressure, and flow rates, instrument calibration, and thorough flushing of the entire system to remove oil, metal particles, and other contaminants. The type of testing and acceptance limits listed in the validation protocol may vary from firm to firm however, compressed air with product contact should be tested for such quality attributes as hydrocarbons, water vapor, and microbial content (typically less than 0.1 CFU/cu. ft.)... [Pg.184]

Often the equipment used to run the analytical methods must also undergo some type of qualification. It is suggested that installation qualification activities be performed at the very least. Many laboratory methods must undergo a calibration before each use, which can serve to eliminate the need for operational and performance qualifications. Again, all of the related analytical calibration/ qualification/validation activities performed must be documented. [Pg.290]

Installation qualification Operational qualification Cleaning validation Ranging studies PLC qualification Process validation... [Pg.316]

Yes Identify level below Qualification Installation Qualification Operational Qualification Performance Qualification Re validation ... [Pg.322]

All protocols, whether for IQ (installation qualification)/OQ (operational qualification) of new equipment or for validating a new process, have the same... [Pg.439]

Figure 1 depicts the most commonly used approach to the qualification process as used in the pharmaceutical industry. It shows a pyramid, which is the best way in which to plan a qualification/validation project. Investing more time in the first phases will save time and money in later and critical phases. If inadequate investment is made during the start-up of a project, the later phases of installation qualification (IQ), operational qualification (OQ), and performance qualification (PQ) will necessarily require an inordinate amount of time and money. The project will be a pyramid again, but now it is inverted. [Pg.480]


See other pages where Validation operational qualification is mentioned: [Pg.60]    [Pg.1041]    [Pg.1058]    [Pg.244]    [Pg.8]    [Pg.8]    [Pg.292]    [Pg.4]    [Pg.35]    [Pg.816]    [Pg.205]    [Pg.328]    [Pg.333]    [Pg.461]    [Pg.514]   
See also in sourсe #XX -- [ Pg.321 , Pg.327 ]




SEARCH



Operation qualification

Operational qualification cleaning validation

Pharmaceuticals process validation operational qualification

Validation process Operational Qualification protocols

© 2024 chempedia.info