Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Validation process Installation Qualification protocols

IQ Installation Qualification protocol OQ Operational Qualification protocol PQ Performance Qualification protocol PV Process Validation protocol PM Preventive Maintenance procedure... [Pg.79]

Enhanced turn-over package Installation qualification protocols Operational qualification protocols Change control initiation Cycle development Performance qualification protocol Process validation protocols Validation final reports Validation package Certificate for use in manufacturing Required protocols and procedures for dry production Required protocols and procedures for liquid and semisolid products... [Pg.200]

The validation process is subject to the following design specifications, user and performance requirements, preparation of a master plan/validation protocol (installation qualification, operational qualification, and performance qualification), execution of the protocol, preparation of a summary report, and on-going validation (and revalidation if changes are made). [Pg.1028]

Validations fall into two types prospective and retrospective. In prospective validation (see flow chart in Figure 2) the validation is done in a sequential manner, involving installation qualification and operational qualification (IQ/OQ) of equipment (e.g., chromatography instrumentation or column hardware). Appropriate calibrations accompany the IQ/OQ. Process qualification, or PQ, involves formal review and approval of a PQ protocol, execution of this protocol, and issuance of a formal PQ report which includes data analysis and recommendations (i.e., approval/certification of the process). If the process is not approved, the report may recommend a redesign or redoing of the validation protocol and, in some cases, a return of the process to process development for further optimization. [Pg.118]

Instrument qualification or validation refers to the process of demonstrating an instrument s suitability for its intended use. The first step is to write protocols to cover the four main qualification elements design qualification, installation qualification, operational qualification, and performance qualification. Another qualification element, re-qualification, can be written as a separate protocol or included as part of the PQ protocol. These protocols must be performed in sequence. If the protocol meets its acceptance criteria, then the next protocol in the sequence can be executed. [Pg.57]

As noted, excipient manufacture should take place using qualified equipment and a validated process. Generally excipient equipment has been in place for many years so that classical methods of qualification, which is done as new equipment is commissioned, are inapplicable. To retrospectively qualify the installation, operation, and performance of equipment, it is suggested to rely on historical records. For installation and operation qualification, a protocol is prepared that illustrates how maintenance and production records will be used to support the hypothesis that the equipment was installed properly and is operating as intended. Then the protocol is executed by reviewing the maintenance and production records for the supporting data. Finally a report is prepared that includes the data from the records, which support the conclusion that the installation and operation of the equipment conforms to protocol requirements. It is suggested that maintenance and production records for a minimum of one year but preferably five years be reviewed. [Pg.380]

All protocols, whether for IQ (installation qualification)/OQ (operational qualification) of new equipment or for validating a new process, have the same... [Pg.439]

In all large and complex systems developed by contract developers, it is normally the practice to perform an SAT. The SAT is the set of activities comprising the system installation, start-up, operational testing, and user orientation performed by the software supplier/integrator in the operational environment. For the purposes of this book, the operational testing performed as part of the SAT is also known as the OQ2. If the SAT is conducted according to approved protocols, test results are properly documented, and test results reviewed and approved by the user and QA, it may not be necessary to repeat the installation and operational qualifications. This provides cost savings and can streamline the validation process. Refer to Sidebar 10-2. [Pg.73]

A significant aspect of compliance is validation of the process through qualifications of the equipment installation and operation, process validation and, recently, the development of a cleaning validation. There are summaries describing how to qualify the installation and operation of equipment, piping, valves and instruments [84], The process validation requires evaluating the critical steps, which effect the quality and purity of the final active drug substance [85]. This involves development of a protocol, which states how the validation is to be conducted and defines the data to be collected. The most important part of the protocol is the development of acceptance criteria for the results. [Pg.295]

An important part of any validation protocol for NIR or other instrumental methods is the process of instrument qualification. In any GMP/GLP facility, instrument performance must be validated. This instrument performance validation, also called instrument qualification, involves three phases [9] installation qualification (IQ), operational qualification (OQ), and performance qualification (PQ). [Pg.115]

Systems specifications provide all the information needed for the technical implementation of the system. This includes hardware, networking connections, and backup requirements as well as all information needed to install, operate, and qualify the performance of the system. It generally includes all of the qualification protocol documents (installation, operation, and performance qualifications) created during the validation process. [Pg.59]

The master plan is finalized during detail engineering. The protocols prepared (IQ s, OQ s and PQ s) and the validation files started during construction. The IQ s (Installation Qualifications) are performable as construction is completing and can be completed by the constructor under supervision. The OQ s (Operational Qualifications) can be performed during the earlier parts of start-up as verification of mechanical completion. The PQ s (Process Qualifications) are performed as start-up completes and continue through the operating life of the plant. For maximum schedule... [Pg.771]

Documented evidence is achieved by preparing written validation protocols prior to doing the work, and writing final reports at the completion of the work. Information must be in writing, otherwise it does not exist, according to the FDA. The process equipment used should undergo installation qualification (IQ) and operational qualification (OQ) to establish confidence that the equipment was installed to specification and purpose and is capable of operating within established limits required by the process. Performance characteristics which may be measured could be uniformity of speed for a mixer or the temperature and pressure of an autoclave, for example. [Pg.324]

It must be proven that a device will be suitable for the intended function in the preparation process by appropriate validation or qualification, see Sect. 34.15. Qualification and validation must be planned, described and documented. Responsibilities must be clear before the vaUdation process starts. Tests, calibrations, inspections and acceptance criteria must be laid down in a pre-approved qualification protocol. Raw and processed data, test results and ccmclusions must be documented. The result is the qualification or vahdation report, including test results and conclusirais. Qualification effort are highly dependent on the criticality of the equipment and the direct or indirect effect (impact) of the device on the quality of the preparation process and product. When purchasing a new device it is often possible to ask the supplier (by quality agreement) to qualify the equipment. This involves, usually, the Installation Qualification (IQ) and the Operational Qualification (OQ), sometimes also parts of the Performance qualification (PQ), although usually the user of the equipment has to take the responsibility for the execution of the PQ (see Sect. 34.10). [Pg.610]

Qualification Verification. Again, the process validation protocol should reference all items that support the validation the procedures, personnel, methods, and equipment. This section therefore lists and summarizes the various installation, operational, and performance/process qualifications completed for the equipment used in the process validation. These qualifications should list each by equipment name and number and qualification and type. A typical verification section is illustrated below. [Pg.316]


See other pages where Validation process Installation Qualification protocols is mentioned: [Pg.8]    [Pg.816]    [Pg.205]    [Pg.830]    [Pg.230]    [Pg.234]    [Pg.46]    [Pg.193]    [Pg.328]    [Pg.333]    [Pg.3722]   
See also in sourсe #XX -- [ Pg.75 ]




SEARCH



Installation Qualification Protocols

Process validation protocols

Processing protocols

© 2024 chempedia.info