Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Sloping trenching

Filtration installations include wrapping the trench of a pavement-edge drain system to prevent contamination of the underdrain placement behind retaining walls and bridge abutments to prevent contamination of the sand blanket placed against the stmcture to allow dissipation of pore pressures in order to avoid failure of the stmcture as silt fences to allow surface mnoff from a site while retaining the soil suspended in the mnoff and on earth slopes beneath larger stone or other overlay materials to prevent erosion of the slope as water escapes from the interior of the slope. [Pg.260]

In terms of dead loads, the shape of the trench in which the pipe will be buried is also a factor. Generally speaking, a narrow trench with vertical sidewalls will impose less of a load on the pipe than will a wider trench with sloping side walls. It is necessary also to know the modulus of soil reaction (E), which is dependent on the type or classification of the native soil, the backfill material that is contemplated, and the desired consolidation of the backfill material. Soil consolidation is important, because it contributes to the strength of a flexible conduit in a buried pipe system. [Pg.212]

An example of the effects of waste settlement can be illustrated by a recent incident at a hazardous waste landfill facility in California.5 At this facility, waste settlement led to sliding of the waste, causing the standpipes (used to monitor secondary leachate collection sumps) to move 60-90 ft downslope in 1 day. Because there was a very low coefficient of friction between the primary liner and the geonet, the waste (which was deposited in a canyon) slid down the canyon. There was also a failure zone between the secondary liner and the clay. A two-dimensional slope stability analysis at the site indicated a factor of safety (FS) greater than 1. A three-dimensional slope stability analysis, however, showed that the safety factor had dropped below one. Three-dimensional slope stability analyses should therefore be considered with canyon and trench landfills. [Pg.1122]

Determination of initial recovery well (or trench) locations is an important design parameter. Floating LNAPL product tends to move in the direction of overall ground-water flow, as determined by the water table gradient. As a well or trench is pumped, the fluids (water and/or oil) migrate toward the area of lower pressure to fill the void. A cone of depression develops that extends outward. The fluid surface exhibits a rapid slope near the well, diminishing to a very low gradient at a distance. [Pg.335]

A drainage system includes a containment system using solid, impermeable floors with perimeter features (curbing, floor slope, or trenches) to limit and control the spread of liquids and a collection system (floor drains or trenches, catch basins, sumps, piping, and manholes) to direct the liquids into a gravity drain system that routes them to an appropriate location out of the unit. [Pg.240]

The surface below pipes in a pipe trench should have a 1% slope toward one side of the trench and toward a drain point so that spills will quickly drain away from the pipes. A drainage channel 10 ft (3 m) from the edge of a pipe trench is desirable for fire protection. [Pg.281]

There are three ways to safe a trench The first method is to slope to the angle of repose the second is benching and the third is shoring. The first two are accomplished with backhoes and live workers, the third with well-trained and organized rescuers. [Pg.97]

Active margin a margin consisting of a continental shelf, a continental slope, and an oceanic trench. [Pg.512]

Many diked areas are unnecessarily flat and level, which allows a liquid spill to spread over the entire surface (CCPS, 1988a). The optimal design for a sloping dike is a simple, one-directional slope away from the tank, leading to a trench or sump that allows for the possibility of remote collection... [Pg.92]

Cost and installation time for 2-ft-wide trench in damp sandy loam sloped i to 1. [Pg.514]

Biddle, J. F., House, C. H., andBrenchley, J. E. (2005). Enrichment and cultivation of microorganisms from sediment from the slope of the Peru Trench (ODP Site 1230). Proc. Ocean Drill. Program Sci. Results. 201, 1—19. [Pg.185]

After the pattern is generated and the trench depth is measured by profilometry, Si02 is deposited and subsequently planarized by CMP. After CMP, the surface is again measured by profilometry and the amplitude of the square wave subsequent to polish is compared to die amplitude prior to oxide deposition. Figure 5.26 shows the ratio of the post-polish CMP amplitude, to the predeposition amplitude. A , vs. oxide removed for several trench widths. Note that the plot of log (A/A ) vs. oxide removed is a straight line. Renteln et al. use this fact to define the metric planarization rate, P, which is equal to the slope of the lines in Figure 5.26. [Pg.158]

Figure 6 Post-CMP nitride and oxide slopes independent vyith silicon trench depth and oxide deposition thickness. All the wafers were polished to approximately the same trench oxide target. Figure 6 Post-CMP nitride and oxide slopes independent vyith silicon trench depth and oxide deposition thickness. All the wafers were polished to approximately the same trench oxide target.
Gutter or trench, sloped from ends to center, drains through wall, down floor on opposite side. Note expansion joint next to trench, 2 brick out from trench wall. Peripheral expansion joint on adjacent floor continues through trench and across brick capping. [Pg.58]

Years ago, it was thought that if the concrete were poured at a uniform depth throughout, the membrane applied, and then the brick walls installed, more concrete could be poured on the bottom, and it could be graded to establish the proper slope. Next, a membrane would be applied over the concrete and side to side bonded to the acid brick walls already installed, then a final course laid on the bottom on top of the membrane and cemented to the brick walls. Obviously, these trenches failed. The membrane on the floor was discontinuous. Acid got into the concrete used to establish the slope, through the acid brick walls, destroying it, and the bottom collapsed. [Pg.248]

A final possibility. Design once again as in the first instance with a uniform, constant depth, place the membrane and lay the walls, then use a polymer concrete castable to establish the slope. If the trench is a long one, the concrete bottom can be stepped at each point where the depth increases by exactly one brick depth. Now, after applying the membrane, the slopes can be established with a polymer concrete without having to worry too much at the material cost of a larger volume of polymer concrete. [Pg.248]

This naturally leads into a consideration of vessel design. The importance of contouring and of expansion joints has been covered earlier other design details common to vessels and trenches have been touched on in Drawings 1,3, 4, 5 (for sloping bottoms), 6 (where there may be a need to control the direction of... [Pg.253]

Chemically resistant masonry joints in clay pipe are rigid. Ground movement, such as settlement, can therefore break the pipe. For this reason it is important that all industrial waste lines be laid with continuous support. No matter what opinion others may have of the stability of the soil in the area where the pipe is to be laid, this writer has never seen any trench excavation, no matter how well prepared, that did not require adjustment to attain the suitable smooth surface and slope after the trenching operation had been completed. These adjustments require fill in some spots and further surface removal in others. In addition bell excavations are required to provide working room to make the joints. After the line is in service, heavy rains, flooding and even percolation of groundwater can cause soil movement above and around the pipe, and eventually, without uniform support, movement will take place that breaks the pipe. [Pg.289]

Plants that handle flammable liquids are usually designed to have slightly sloping ground or use drainage ditches or trenches to control runoff so that pools do not form. Drainage ditches and slopes should always direct flow away from sources of ignition. [Pg.499]

Carson, B., von Huene, R. and Arthur, M. 1982. Small-scale deformation structures and physical properties related to convergence in Japan Trench slope sediments. Tectonics, 1 277-302. [Pg.89]

Lundberg, N. and Casey Moore, J. 1982. Structural features of the Middle America Trench slope off southern Mexico, Deep Sea Drilling Project Leg 66. In J.S. Watkins, J. Casey Moore et al. (Editors), Initial Reports of the Deep Sea Drilling Project, 66. US Government Printing Office, Washington DC, pp. 793-805. [Pg.89]


See other pages where Sloping trenching is mentioned: [Pg.231]    [Pg.672]    [Pg.176]    [Pg.231]    [Pg.672]    [Pg.176]    [Pg.1350]    [Pg.232]    [Pg.1046]    [Pg.106]    [Pg.52]    [Pg.6]    [Pg.216]    [Pg.242]    [Pg.98]    [Pg.150]    [Pg.412]    [Pg.264]    [Pg.3835]    [Pg.638]    [Pg.224]    [Pg.248]    [Pg.254]    [Pg.376]    [Pg.1043]    [Pg.152]    [Pg.158]    [Pg.168]    [Pg.171]    [Pg.605]    [Pg.606]   
See also in sourсe #XX -- [ Pg.214 ]




SEARCH



Slope

Sloping

Trench

© 2024 chempedia.info