Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Excavations Construction

Perry W. (1963). Electro-osmosis dewaters foundation excavation. Construction Methods and Equipment 49(9) 116-119. [Pg.658]

ABSTRACT According to relevant documents and payment in the form of questionnaires, 224 cases of the domestic excavation accident in past two decades are collected in this paper. Based on processing and analysis of accident cases, the common risk events and factors are determined in the construction of deep excavation. Meanwhile the relativity between risk of quality and risk of safety and risk of investment is analyzed according to causes and losses of the accident, and the graph of macroscopic logical relation established between the risk of three objective dimension, which provides a reference for comprehensive risk management excavation construction process and basehne data for the theoretical analysis of risk. [Pg.401]

In this paper, a cut rock slope was under excavation construction in the highway project. The slope angle was about 73°, slope length was about 180 m and slope height was about 50 m. [Pg.275]

For corrosion protection in soils, the anodes can be brought close to the object to be protected in the same construction pit so that practically no further excavations are needed. By connecting anodes to locally endangered objects (e.g., in the case of interference by foreign cathodic voltage cones) the interference can be overcome (see Section 9.2.3). [Pg.205]

In mining and, more recently, the construction of underground storage tanks for liquefied natural gas, it is often necessary to sink a shaft through water-logged ground. The requirement is to form a temporary cofferdam to permit excavation and the building of a permanent liner. [Pg.225]

Temporary dirt roads (poorly maintained) -Heavy construction and excavation-----------... [Pg.273]

Soil surveys relating to construction work require samples from at least the depth of excavation water seepage may cause cross-contamination of land. Some guidelines for the classification of contaminated soils are summarized in Table 13.11 some materials are difficult to dispose of safely on land (Table 13.12). [Pg.345]

An embankment refers to a volume of longitudinal earthen material that is placed and compacted for the purpose of raising the level of a roadway (or railway) above the level of the existing ground surface. A fill refers to a volume of earthen material that is placed and compacted for the purpose of filling in a hole, cavity, or excavation. Embankments or fills are constructed of materials that usually consist of soil, but may also include aggregate, rock, or crushed paving material. [Pg.186]

After a landfill site has been chosen and a basin has been excavated, the basin is lined with one or more layers of water-retaining material (liners) that form a leachate bathtub. The contained leachate is pumped out through a network of pipes and collector layers. Liners may be constructed of synthetic polymer sheets or of clay. U.S. EPA s MTG3A7 relies on a composite liner that utilizes the advantages obtained from combining both liner systems. [Pg.1118]

Well construction minimizes the generation of significant quantities of potentially hazardous soils in contrast to significant volumes potentially generated by trench excavation. [Pg.217]

Develop mix design Determine end use Excavate and produce product Confirm effectiveness Construct end use (i.e., road base, pavement, etc.)... [Pg.296]

At locations where aboveground blending takes place, the resulting soil material can be placed back in the original excavation (or selected location) and compacted to the desired density. If the solidified material is to have a desired structural strength (i.e, subbase, pavement, controlled fill, etc.) it can be compacted by conventional construction equipment (vibrating or sheeps-foot rollers). [Pg.298]

Trenches were constructed using conventional earthmoving equipment. During construction, air monitoring was continued to assure that explosive conditions were not present. However, odors persisted from the freshly excavated soils but disappeared within a few days. Operation of this trench system continues throughout frost-free seasons and has proved very successful. Initially, approximately 5 bar-... [Pg.362]

Because these barriers are not anchored into the roadway, they do not require excavation or other related construction for installation. In contrast, they can be assembled and made operational in a short period of time. The primary shortcoming to this type of design is that these barriers may move if they are hit by vehicles. Therefore, it is important to carefully assess the placement and anchoring of these types of barriers to ensure that they can withstand the types of impacts that may be anticipated at that location. Table 9.5 lists the pros and cons of portable/removable barricades. [Pg.166]

The major cost factors of an evaporation pond include pond liners, land preparation, excavation and clearing, site surveying, bank construction, pumps, control systems, disposal of precipitated solids, maintenance and geotechnical investigation of the site (Singh and Christen 2000). Of these, pond liners typically represent the greatest cost (Nicot et al. 2009). [Pg.63]

During the next phase of construction, the basement and sub-basement of the house are dug. This excavation draws tens of thousands of tons of B (and sometimes C) Horizon soils to the surface. With little or no resale value, these soils are simply spread around the surface of the site to serve as the basis for landscaping after construction is complete. Starved of organic material and loaded with minerals (not to mention plaster, cement, lumber, and other debris), these soils are a prohibitively poor base for planting. It is little wonder mulch is an increasingly popular ground cover in the suburbs. [Pg.40]

Unit cost values for excavation, geomembranes, or clay cell liners and other construction costs are identical for both anaerobic and aerobic passive-treatment systems. [Pg.475]

The technology was designed to be applied in situ for the treatment of contaminants in shallow soil. However, it can be applied as an ex situ treatment, for excavated soils, in specially constructed shallow treatment basins. [Pg.721]

The primary disadvantage of an aeration curtain is that contaminated soil must be excavated during construction of the curtain. [Pg.899]


See other pages where Excavations Construction is mentioned: [Pg.104]    [Pg.230]    [Pg.114]    [Pg.161]    [Pg.104]    [Pg.230]    [Pg.114]    [Pg.161]    [Pg.1691]    [Pg.180]    [Pg.31]    [Pg.188]    [Pg.906]    [Pg.273]    [Pg.811]    [Pg.1331]    [Pg.613]    [Pg.646]    [Pg.366]    [Pg.303]    [Pg.225]    [Pg.36]    [Pg.26]    [Pg.174]    [Pg.361]    [Pg.386]    [Pg.165]    [Pg.275]    [Pg.146]    [Pg.643]    [Pg.711]    [Pg.970]    [Pg.970]   


SEARCH



Excavating

Excavations

© 2024 chempedia.info