Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Team work issues

While you may well have other objectives, these seem to be the principal choices. They can be seen as forming a progression. From one-to-one collaboration you can develop into team-working, which in turn can lead to synergy. The levels are of course not mutually exclusive you can work on all three simultaneously. Later in the chapter we shall consider some of the distinctive issues involved in working at each of the levels. But first we consider two Issues that are relevant to all three values and style. [Pg.177]

A second immediate success was in DMPK. When a project team working on ITK realized that their early compounds had safety problems due to inhibition of P-450, the ITK team collaborated with the SYK team who had had the same issue and had resolved it after a 2-year effort. ITK was able to benefit from the recent knowledge that was gained in solving the SYK problem. As a result, ITK required 6 months less to successfully design lead compounds without P-450 inhibition liabilities. [Pg.800]

Root cause of customers problems Finding the root cause(s) of the problems faced by the customers was not always trivial. Hence, the project team worked with both customers and Valvex personnel to figure out where the real problems were and what could be done to address the issues. [Pg.221]

Thematic analysis also showed that the most frequently identified issues are environmental - the physical space and design of the hospital accoimted for just over 25 percent of all issues identified, followed by equipment (23 percent) and clinical processes (20 percent). Many of these issues were unresolvable within the one month time frame set because they related to the environment in which healthcare teams work. They are therefore not easily fixed. [Pg.145]

Introduction Team working To provide information about the overall aims of the day. Team building. Identify pupils initial views of genetic issues. Introduce the key aims. Manage activity. Help pupils to clarify views. [Pg.80]

Quality circles Quality circles are teams of staff who are volunteers. The team selects issues or areas to investigate for improvement. To work properly teams have to be... [Pg.384]

These steps also work well for teams addressing issues other than safety. For example, you might use this process to help establish and clarify your organization s basic values or to clarify the type of personal interactions required to ensure the success of other improvement initiatives. [Pg.275]

The book does not focus on occupational safety and health issues, although improved process safety can benefit these areas. Detailed engineering designs are outside the scope of this work. This book intends to identify issues and concerns in batch reaction systems and provide potential solutions to address these concerns. This should be of value to process design engineers, operators, maintenance personnel, as well as members of process hazards analysis teams. While this book offers potential solutions to specific issues/concerns, ultimately the user needs to make the case for the solutions that provide a balance between risk... [Pg.1]

The pump had been awaiting repair for several days when a work permit was issued at 8 00 AM. on the day of the fire. The foreman who issued the permit should have checked, before doing so, that the pump suction and delivery valves were shut and the drain valve open. He claimed that he did so. Either his recollection was incorrect or, after he inspected the valves and before work started, someone closed the drain valve and opened the suction valve. When the valves were closed, there was no indication on them of why they were closed. A worker might have opened the suction valve and shut the drain valve so that the pump could be put on line quickly if required. A complicating factor was that the maintenance team originally intended to work only on the pump bearings. When they found that they had to open up the pump they told the process team, but no further checks of the isolations were carried out. [Pg.33]

The separation plant had been running smoothly for several weeks and the planned shutdown was some time away. On the day of the incident a number of unusual events occurred which contributed to its development. Shortly after the start of his day shift, the control room operator received a high vibration alarm from booster pump A in the crude fluid separation building. Following normal procedure, he switched over to the standby pump (pump B), switched off pump A, and told his supervisor of the alarm. The supervisor subsequently organized a work permit for work to be carried out on pump A by the day shift maintenance team. The permit was issued and repair work... [Pg.294]

I published a short paper in a somewhat obscure conference proceedings in which I disagreed with Brush.15 I then approached Worrall to see if he wanted to team-up with me to take a closer look at the issue. At first he did not seem too interested but this changed after I became a post-doctoral fellow at the LSE and continued to press Worrall to work on this project. [Pg.7]


See other pages where Team work issues is mentioned: [Pg.185]    [Pg.185]    [Pg.356]    [Pg.341]    [Pg.1553]    [Pg.342]    [Pg.189]    [Pg.977]    [Pg.981]    [Pg.1804]    [Pg.211]    [Pg.369]    [Pg.84]    [Pg.477]    [Pg.173]    [Pg.460]    [Pg.88]    [Pg.13]    [Pg.34]    [Pg.428]    [Pg.609]    [Pg.211]    [Pg.397]    [Pg.309]    [Pg.189]    [Pg.72]    [Pg.514]    [Pg.13]    [Pg.90]    [Pg.63]    [Pg.2269]    [Pg.16]    [Pg.232]    [Pg.171]    [Pg.561]    [Pg.18]    [Pg.39]    [Pg.207]    [Pg.312]   
See also in sourсe #XX -- [ Pg.37 ]




SEARCH



Team working

© 2024 chempedia.info