Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Loads heat required into

To evaluate the input required for a process, one must first determine the heat required into the load, which is discussed in sections 2.1.1. and 2.1.2. below. The means by which the load is heated is usally a furnace, kiln, or oven, but these means themselves require some heat over and above what they deliver to the load. [Pg.26]

The total heat requirement is thus around 599.98 kj, which is about 548.81 kj more than the heat available from the reaction. This calculation, however, does not take into account the inevitable heat losses due to the nonadiabatic conditions in the reactor. An estimate of these heat losses can be made by considering the industrial practice for aluminothermic chromium metal production. The charge is preheated to about 500 °C before loading into the aluminothermic crucible. This operation adds about 96.65 kj (i.e., 48.9 cal deg-1 475) of heat to the system. It, therefore, appears that around 41.84 kj (96.65 kj - 54.81 kj) of heat is lost due to radiation and convection for every mole of chromium sesquioxide reduced to the metal by the aluminothermic process. [Pg.392]

The double-split-cone loading mechanism worked well. The cone was designed to match the circumferential stiffness of the test specimen. To achieve minimum heat loss into the dewar, the required axial load and the actuator rod cross... [Pg.347]

In the rotary kiln of cement works, clay and lime are sintered or burnt into cement clinker. The reactor is run in counterflow Primary firing heats the material to approx. 1,400 °C, secondary firing in the loading area ensures calcinations at approx. 900 °C. Approximately 3.3 GJ energy are required for production of 1 Mg cement [20]. To reduce the energy costs, which account for approx. 50 % of the production costs, substitute fuels such as old tires, used oil, paint sludges, sawdust or refuse-derived fuels are used. As much as 30 % of the total heat requirement of a plant have been covered by these secondary fuels [21], the solid residues of which are integrated into the product [19]. [Pg.410]

The required available heat for the soak zone will be the sum of (a) the remaining heat needed into the loads to heat them to good quality (b) heat losses to and from refractory, hearth materials, openings, and water-cooled devices and (c) heat absorbed by infiltrated air in warming to zone temperature. [Pg.166]

Because of the complexity of combustion kinetics, coupling kinetics and hydrodynamics into a single comprehensive model is not generally pursued. Instead, many successful hydrodynamic studies vary operational parameters and study the effect on combustion performance parameters. Moe et al. [22] characterized combustion performance with seven parameters (1) heat transfer, (2) combustion efficiency, (3) bottom ash/total ash, (4) bed grain size, (5) limestone utilization, sulfur capture, and Ca/S (6) CO emissions, and (7) NO and NjO emissions. Eight operational variables they listed that impact one or more of the performance parameters were (1) bed temperature—affects carbon burnout, emissions, sorbent utilization, and heat absorption (2) primary/secondary air split—impacts NO emissions, temperature distribution, and pressure drop (3) excess air—changes thermal efficiency, emissions, and carbon burnout (4) solids circulation rate—controls load, heat absorption pattern, heat transfer coefficient, and pressure drop (S) fuel size—determines carbon burnout, bed vs. fly ash split, and pressure drop (6) limestone size—determines Ca/S ratio required and bed vs. fly ash split (7) Ca/S ratio—impacts sulfur capture, limestone utilization, waste/disposal volumes, particulate generation, and emissions and, (8) load—effects heat absorption, emission, carbon burnout, thermal efficiency, and temperature distribution. [Pg.276]

To compute the heat loads, we require the vapor flow rates into the condenser and out of the reboiler. These are obtained by a series of total and component balances, starting with those taken over the entire column. Thus,... [Pg.287]

The acceptance tested spacecraft and the certified fueled reactor module were to be received by KSC. The electrically heated power unit was to be replaced with the fueled power unit. Cutting and seal welding these joints was considered a critical, complex task, requiring extensive preparation and training. The HeXe coolant is purified, loaded, and sealed into the RM. Final functional, electrical, and software checks were to be performed. A preference existed to perform slider motion checks and zero-power critical tests at KSC prior to launch if this is appropriate from a regulatory standpoint (this issue had not been resolved at the time of project termination). The assembled spacecraft was to be mated to the launch vehicle and prepared for launch. [Pg.762]

Reinforced Thermoplastic Sheet. This process uses precombined sheets of thermoplastic resin and glass fiber reinforcement, cut into blanks to fit the weight and size requirements of the part to be molded. The blanks, preheated to a specified temperature, are loaded into the metal mold and the material flows under mol ding pressure to fiU the mold. The mold is kept closed under pressure until the temperature of the part has been reduced, the resin solidified, and demolding is possible. Cycle time, as with thermosetting resins, depends on the thickness of the part and the heat distortion temperature of the resin. Mol ding pressures are similar to SMC, 10—21 MPa (1500—3000 psi), depending on the size and complexity of the part. [Pg.96]

Great care is needed in the design of autoclaves and sterilization cycles because of the requirement for the presence of moisture. The autoclave must be loaded to allow complete steam penetration to occur in all parts of the load before timing of the sterilization cycle commences. The time required for complete penetration, the so-called heat-up time, varies with different autoclave constmction and different types of loads and packaging materials. The time may not exceed specific limits in order to guarantee reproducibility and, for porous loads, saturated steam. The volume of each container has a considerable effect on the heatup time whenever fluids are sterilized. Thermocouples led into the chamber through a special connector are often employed to determine heatup times and peak temperatures. The pressure is refleved at the end of each sterilization cycle. Either vented containers must be used or... [Pg.407]


See other pages where Loads heat required into is mentioned: [Pg.362]    [Pg.245]    [Pg.198]    [Pg.292]    [Pg.347]    [Pg.347]    [Pg.172]    [Pg.435]    [Pg.239]    [Pg.362]    [Pg.347]    [Pg.347]    [Pg.118]    [Pg.347]    [Pg.581]    [Pg.362]    [Pg.392]    [Pg.730]    [Pg.187]    [Pg.115]    [Pg.86]    [Pg.71]    [Pg.313]    [Pg.244]    [Pg.622]    [Pg.154]    [Pg.362]    [Pg.336]    [Pg.283]    [Pg.172]    [Pg.420]    [Pg.490]    [Pg.257]    [Pg.466]    [Pg.105]    [Pg.480]    [Pg.118]    [Pg.400]    [Pg.431]    [Pg.504]   
See also in sourсe #XX -- [ Pg.25 , Pg.26 , Pg.27 ]




SEARCH



Heat load

Heat required

© 2024 chempedia.info