Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Implementation process objectives

SOCOPSE (http // www.socopse.se/) was an EU-funded project (2006-2009) within the sixth framework programme (FP6-2005-global-4, Topic II 3.1), with the overall objective to support the implementation process for the WFD by providing guidelines and a decision support system (DSS) for the management of priority substances (PS). [Pg.378]

In addition to the implementation process, evaluation of the project s success is the core of a restoration project. However, many projects do not take this final check, which is a prerequisite for adaptive management, into consideration. Bernhardt et al. [23] found that only 10% of project records (out of 37,099 projects) indicated that any form of assessment or monitoring was carried out. In most European countries, the estimated proportion of success evaluation is in the same range or even lower. Project evaluation through systematic data collection serves to verify whether the project objectives that were defined during the planning phase have been achieved [24]. Therefore, project evaluation is the process of examining the... [Pg.256]

Once the materials have been sterilized, interventions near either the formulation or product contact surfaces/parts should be minimized. Direct handling of these materials should only be done with sterilized tools or implements nonsterile objects, such as operator gloves, should never directly contact a sterilized surface. Sampling, filter integrity testing, process connection, and other activities should all be designed to eliminate the need for personnel exposure to sterile items. [Pg.126]

Abstract This contribution deals with the modeling of coupled thermal (T), hydraulic (H) and mechanical (M) processes in subsurface structures or barrier systems. We assume a system of three phases a deformable fractured porous medium fully or partially saturated with liquid and a gas which remains at atmospheric pressure. Consideration of the thermal flow problem leads to an extensively coupled problem consisting of an elliptic and parabolic-hyperbolic set of partial differential equations. The resulting initial boundary value problems are outlined. Their finite element representation and the required solving algorithms and control options for the coupled processes are implemented using object-oriented programming in the finite element code RockFlow/RockMech. [Pg.199]

The second level of a present implementation is considered nearly fulfilled in Table 9, i.e., F = 8. Total fulfilment would decrease the expected frequency a little bit F = 7). As the staggered list of measurements follows Guttman, the judgement process ends with the first measurement not implemented. Every Objective is treated the same way eventually resulting in 39 risks. [Pg.1880]

These sections logically follow the previous assessment and prioritization requirements. They require that documented processes shall be established to set objectives (Section 4.3) and to implement those objectives, an element of which is allocating the necessary resources (Section 4.4). As feedback is received on the application of provisions in the standard, objectives are to be modified in accord with the continual improvement process. [Pg.19]

In the planning processes, occupational health and safety management systems issues are identified, analyzed, and prioritized. Those issues are defined in the standard as hazards, risks, management system deficiencies and opportunities for improvement. After the identification and analysis process, objectives are then to be established that offer the greatest opportunities for improvement. The following steps are to draft a documented implementation plan to achieve the objectives and to allocate the necessary resources. [Pg.199]

Moderate (3) Sensitivity analysis for platming performed Medium corporate and process capability to address risk Response implemented part objective achieved Most emergency/contingency in place not rehearsed... [Pg.36]

Objectives and targets. Table E-9 describes the progress that Cultor has made in implementing the objectives detailed in its 1995 Environmental Report. New objectives are also given, linked to four key areas implementation of Cultor s sustainable development value process, the environment, quality, and regulatory and ethical issues. The objectives and corporate target objectives are updated annually. [Pg.290]

The thermodynamics and physical properties of the mixture to be separated are examined. VLE nodes and saddles, LLE binodal curves, etc, are labeled. Critical features and compositions of interest are identified. A stream is selected from the source Hst. This stream is either identified as meeting all the composition objectives of a destination, or else as in need of further processing. Once an opportunistic or strategic operation is selected and incorporated into the flow sheet, any new sources or destinations are added to the respective Hsts. If a strategic separation for dealing with a particular critical feature has been implemented, then that critical feature is no longer of concern. Alternatively, additional critical features may arise through the addition of new components such as a MSA. The process is repeated until the source Hst is empty and all destination specifications have been satisfied. [Pg.450]

By attempting to maintain process conditions at or near their design values, the process controls so attempt to prevent abnormal conditions from developing within the process. Although process controls can be viewed as a protective layer, this is really a by-product and not the primaiy func tion. Where the objective of a function is specifically to reduce risk, the implementation is normally not within the process controls. Instead, the implementation is within a separate system specifically provided to reduce risk. This system is generally referred to as the safety interlock system. [Pg.796]

The first major objective for the inherent safety review is the development of a good understanding of the hazards involved in the process. Early understanding of these hazards provides time for the development team to implement recommendations of the inherent safety effort. Hazards associated with flammability, pressure, and temperature are relatively easy to identify. Reactive chemistry hazards are not. They are frequently difficult to identify and understand in the lab and pilot plant. Special calorimetry equipment and expertise are often necessary to fully characterize the hazards of runaway reactions and decompositions. Similarly, industrial hygiene and toxicology expertise is desirable to help define and understand health hazards associated with the chemicals employed. [Pg.117]

Reducing and eliminating hazards and their associated risks is the second major objective. Applying inherent safety principles early in the product/process development effort provides the greatest opportunity to achieve the objectives of the inherent safety review process for the project at hand. If these principles are applied late in the effort the results may have to be applied to the project after next as the schedule may not permit implementation of the results. [Pg.117]

The employer issues a hot work permit for hot work operations conducted on or near a covered process. The permit documents that the fire prevention and protection requirements in 29 CFR 1910.252(a) have been implemented prior to beginning the hot work operations it indicates the date(s) authorized for hot work and identifies the object on which hot work is performed. The permit is kept on file until completion of the hot work operations. [Pg.32]


See other pages where Implementation process objectives is mentioned: [Pg.222]    [Pg.79]    [Pg.740]    [Pg.18]    [Pg.419]    [Pg.456]    [Pg.229]    [Pg.22]    [Pg.170]    [Pg.56]    [Pg.173]    [Pg.55]    [Pg.148]    [Pg.1700]    [Pg.1735]    [Pg.59]    [Pg.79]    [Pg.110]    [Pg.228]    [Pg.221]    [Pg.392]    [Pg.63]    [Pg.17]    [Pg.245]    [Pg.64]    [Pg.72]    [Pg.74]    [Pg.76]    [Pg.61]    [Pg.535]    [Pg.535]    [Pg.536]    [Pg.757]    [Pg.451]    [Pg.139]   
See also in sourсe #XX -- [ Pg.56 ]




SEARCH



Process Objectives

Process implementation

© 2024 chempedia.info