Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Procedures development costs

Traditionally the PERT diagram did not involve costs, but in the early 1960s a plan called PERT/Cost was developed that was similar to the cost-control concepts of CPM. Some authors claimed they were now essentially the same. PERT/Cost involves obtaining one cost for each activity. If the expected time were,the same as the normal time, the procedure for cost control would be the same as for a CPM system. The PERT system can also be easily adapted to the method presented for speeding up projects (crashing). The remarks made previously about scheduling and obtaining time estimates apply equally well to PERT and CPM. [Pg.386]

Current syntheses of SNTs are based on the severe conditions such as extreme pH condition and high temperature and pressure. However, other works which in mild condition required high complicated surfactants as template which requires tedious work-up. We develop the method which provided rather convenient and simple route for the fabrication of SNT at ambient temperature using glycyldodecylamide and in neutral pH. Moreover, the neutral synthetic procedure enabled cost-effective recovery of amphiphiles and environmentally friendly. [Pg.329]

There is a cost associated with the effort needed to prepare these nanostructured materials building blocks must be found and suitably functionalized tailored linking reagents are required air sensitive handling procedures developed and byproducts carefully removed. It is therefore appropriate to ask, has the effort and expense lead to new and better catalysts ... [Pg.159]

The present contract calls for reimbursement of all allowable expenses, excluding contractor costs disallowed by the federal acquisition regulations, such as business development costs. A small base fee was negotiated as profit. The disallowed expenses must be covered by the base fee. The contractor receives a base fee during execution of the contract, and only in the most unusual circumstances is any part of this fee denied. An additional 3 percent of the contract value is set aside as an incentive fee that can be earned by superior performance. The federal acquisition regulations that govern procurement and acquisition procedures undertaken with federal funds are applicable to both materiel and contract services for closure of JACADS... [Pg.35]

In order to develop cost-effective and environmentally friendly chemical processes at the industrial scale, it is essential to integrate biocatalysis and modem chemical catalysis to produce manufacturing routes with fewer synthetic steps, reducing waste steams and improving overall synthetic yields. Normally, in these tandem procedures, the initial step is the preparation of the intermediate by... [Pg.213]

Effective composite sol-gel adsorbents of water vapor can be prepared in a one-step procedure using ethyl silicate 40 as a cost-effective silica precursor. Adsorption properties exhibited by the materials thus obtained are comparable with those of the samples obtained from the more complex procedure developed previously which made use of tetraethoxysilane. [Pg.859]

How to Apply for Designation as an Orphan Product is an FDA guideline providing useful definitions of a rare disease, of a scientific rationale for a therapy, and of the standard of potential clinical superiority. It also provides a detailed application outline and developmental procedure. The document s final section describes the unusual situation in which a nonorphan indication may qualify if there is no reasonable expectation of recovering development costs. [Pg.68]

To calculate several of the cost items listed in Table 2.1, requires the depreciable and fixed capital costs. The depreciable capital cost is the capital required for equipment and its installation or modification in the process, and all the facilities required to operate the process. There is some variation in the definition of fixed capital cost. References [1-5], define the fixed capital as consisting of the depreciable capital cost, land cost, and site or land development cost. Woods [10], however, omits land cost and land development cost so that that the fixed capital cost equals the depreciable capital cost. We will adopt the first definition here. For now, assume that we know the depreciable capital cost. We will develop a procedure for its evaluation later. In Example 2.1 estimate the production cost using Table 2.1. [Pg.55]

Chapter 8 summarizes why operating and maintenance procedures are a critical part of Process Safety Management, the typical costs associated with procedure development, and the return on investment. [Pg.9]

The following sections outline the costs you can expect to encounter during a procedure development project. Three main costs associated with procedure development are the time involved to... [Pg.109]

Since time is a major cost factor in procedure development, tracking procedure development progress is important so that you remain on schedule. There are many alternatives to consider in deciding how to track a procedure project. For the writers, a measurement of the number of first drafts sent to review is an obvious choice. The reviewers can often cause a major delay, so there needs to be some way to know where a specific procedure is at all times (and a phone number to call to get it moving). However, the only datapoint that really matters is Are the procedures approved and available when you need them ... [Pg.110]

Table 14.3 summarizes comparative data showing the increased sensitivity of the Microtox Chronic Test when compared with the standard Microtox Acute Test The chronic test shows an average 50 times greater sensitivity over the acute test for the compounds tested. Table 14.4 compares this new chronic test method with die Ceriodaphnia dubia chronic test procedure developed by the US EPA. These comparative data show similar sensitivities for these 2 chronic test methods. Additional comparative studies using these 2 test methods are underway using complex environmental samples. These results will be published in the near future and should reermfirm the utility of diis relatively simple, rapid, and cost-effective alternative chronic test procedure. [Pg.221]


See other pages where Procedures development costs is mentioned: [Pg.497]    [Pg.1]    [Pg.1]    [Pg.107]    [Pg.108]    [Pg.108]    [Pg.109]    [Pg.110]    [Pg.111]    [Pg.112]    [Pg.497]    [Pg.1]    [Pg.1]    [Pg.107]    [Pg.108]    [Pg.108]    [Pg.109]    [Pg.110]    [Pg.111]    [Pg.112]    [Pg.242]    [Pg.82]    [Pg.89]    [Pg.276]    [Pg.228]    [Pg.99]    [Pg.78]    [Pg.238]    [Pg.100]    [Pg.3]    [Pg.129]    [Pg.2]    [Pg.17]    [Pg.59]    [Pg.32]    [Pg.217]    [Pg.47]    [Pg.120]    [Pg.164]    [Pg.111]    [Pg.219]    [Pg.365]    [Pg.53]    [Pg.26]   
See also in sourсe #XX -- [ Pg.108 ]




SEARCH



Development costs

Procedure development

Procedure development procedures

© 2024 chempedia.info