Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Level plant loading

Level plant loading Efforts to reduce variability in production at the business unit and supply chain levels. Level plant loading is considered a best practice for achieving effective supply chains. Drumbeat and takt time are related terms. [Pg.537]

The plant control system functions to limit temperature rates of change during plant load change and upset events. This is achieved at two different levels. In the time asymptote the control system through control variable set points (with values assigned as a function of steady-state power) takes the plant to a new steady-state condition. The set point values are chosen so that hot side temperatures remain little changed. In the shorter term the control system manages the dynamic response of the plant so that the transition between steady states is stable and with minimal overshoot of process variables. [Pg.420]

Cold pilot-plant tests are presently in progress using 2-inch diameter pulsed plate columns in continuous countercurrent flow. Synthetic Zr-Al high-level waste loaded with 0.2 g/L Ce(III) is being used as feed and 20 volume % DHDECMP in 2 1 decalin-DIPB as extractant. Cerium is being used as an americium simulant. To date, three complete cycles have been run including a solvent recycle wash with Na2C03. No major problems have been encountered. [Pg.392]

As the plant load decreases the generators operate at a decreasing load factor. When each generator has become unloaded to the level set by the lower load factor then the PMS should advise the operator to shut down one generator. This sequence can be repeated until only one generator is running. [Pg.446]

Production leveling—in other words, smoothing of volume as well as variety to achieve uniform plant loading—is imperative for JIT implementation. What would happen if the production volume... [Pg.545]

Carry out structural calculation of loads and stresses from temporary plant/loadings and how these might change if bed levels or wave, water levels and current conditions change. [Pg.66]

In the turbine-following-reactor control mode (i.e., turbine-follows-reactor), station loads are made to follow the reactor output. This is achieved by the steam generator pressure-control program, which adjusts the plant loads in order to maintain a constant steam generator pressure. This mode is used at low reactor power levels, during startup or shutdown, when the steam generator pressure is insensitive to reactor power. It is also used in some upset conditions when it may not be desirable to maneuver reactor power. [Pg.161]

Figure 10.15 NaS battery load levelling plant built by NGK Insulators (Japan). [Pg.296]

With a steam turbine, the turboeompressors ean be readily matehed to the different plant operating eonditions. Under eontinuous load, this type of installation is powered by the steam resulting from ammonia eombustion. Consequently, an outside steam supply is needed for startup. This may be a separate boiler or another external souree with live-steam properties not neeessarily eorresponding to those obtained from the nitrie aeid plant. The steam turbine must be of robust design beeause of the different pressure and temperature levels. [Pg.116]

Specific reduction targets for the different processes are not well established. In the absence of specific pollution reduction targets, new plants should always achieve better than the industry averages and should approach the load-based effluent levels. [Pg.71]

The practical implications of this experiment are that when evaluating the effects of shift work due to circadian effects, the type of task being carried out by the worker must be taken into account. For example, skill-based tasks would be expected to exhibit the performance changes characteristic of low memory load tasks, whereas performance variations in knowledge-based tasks would be expected to follow the pattern of high memory load tasks. Performance on rule-based tasks may depend on the degree of frequency of use of the rules, which in turn may determine the memory load. If these results were confirmed by further process plant studies, it would have implications for when different types of operation (involving different levels of memory load) should be scheduled to reduce circadian rhythm effects and minimize errors. [Pg.118]

On the other hand, when workers are seriously under-loaded, they might not be very alert to changing process conditions. Many of the problems of plant automation are common to other situations of task underload. To increase the level of activity in monitoring tasks, additional tasks can be assigned, such as calculating the consumption of fuels, the life of a catalyst, the efficiency of the furnace and so on. Meister (1979) provides a summary of research on team organization. [Pg.143]

About 2.5 million tons (2.3 million tonnes) of coal arc burned daily in U.S. power plants. This is equivalent to roughly 21,000 railcars in transit, so it is apparent that coorditiatiiig production and cotistimp-tioii is no easy task. Accidents, rail strikes, natural disasters (e.g., floods that take out bridges and rail lines) and severe weather (e.g., deep river freezes that halt barge traffic) can all severely disrupt deliveries for utility customers dependent on a reliable coal supply for base load plants. Nonetheless, to reduce costs U.S. utilities have significantly reduced typical inventory levels over time. Wliereas a coal inventory of ninety days of supply was once typical, inventories now frequently run in the range of thirty to forty-five days. [Pg.264]

For most smaller operators, the waste water discharge from pretreatment equipment, blowdown receivers, and FSHR equipment typically discharges into a city sewer. Most larger factories, process plants, and power stations, on the other hand, incorporate some form of waste water treatment facility to balance the pH level, remove oils and pre-cipitable solids, or otherwise reduce the contamination load before the discharge of water from the site. [Pg.72]

Higher than expected hardness levels are usually attributed to inadequate chemical addition or poor sludge recirculation. High turbidity is often attributable to fluctuating hydraulic loading on the process plant. [Pg.313]


See other pages where Level plant loading is mentioned: [Pg.434]    [Pg.434]    [Pg.90]    [Pg.53]    [Pg.79]    [Pg.74]    [Pg.151]    [Pg.212]    [Pg.268]    [Pg.319]    [Pg.287]    [Pg.93]    [Pg.170]    [Pg.417]    [Pg.98]    [Pg.18]    [Pg.345]    [Pg.268]    [Pg.208]    [Pg.1126]    [Pg.2401]    [Pg.2499]    [Pg.44]    [Pg.745]    [Pg.765]    [Pg.154]    [Pg.376]    [Pg.38]    [Pg.210]    [Pg.315]    [Pg.421]    [Pg.444]    [Pg.483]    [Pg.251]    [Pg.59]   
See also in sourсe #XX -- [ Pg.537 ]




SEARCH



Load leveling

Load levelling

© 2024 chempedia.info