Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Shunt reactors

When the systems that are series compensated are eonneeted to a lightly loaded transformer or shunt reactor, under certain line conditions (Section 24.4). [Pg.558]

I Shunt reactors These are provided as shown in Figure 24.23 to compensate for the distributed lumped capacitances, C , on EHV networks and also to limit temporary overvoltages caused during a load rejection, followed by a ground fault or a phase fault within the prescribed steady-state voltage limits, as noted in Table 24.3. They ab.sorb reactive power to offset the charging power demand of EHV lines (Table 24.2, column 9). The selection of a reactor can be made on the basis of the duty it has to perform and the compensation required. Some of the different types of reactors and their characteristics are described in Chapter 27. [Pg.798]

Figure 27.8 Use of a shunt reactor to compensate for the reactive power... Figure 27.8 Use of a shunt reactor to compensate for the reactive power...
Instantaneous and time delay overcurrent relays are the most common protective devices used on shunt reactors, capacitors and station service equipment. [Pg.421]

Cfj and Q in the figure are capacitances that represent bushings and shunt reactors,... [Pg.228]

The world s first long 500-/400-kV cable was installed in Canada by BC Hydro in 1984 [23,24-25]. This 500-kV AC submarine cable is a double-circuit line that connects Vancouver Island to mainland Canada through Texada Island. The distance between Vancouver Island and Texada Island is approximately 30 km the distance between Texada Island and mainland Canada is approximately 8 km. In between, the line has an overhead section on Texada Island. Shunt reactors totaling 1080 MVar were installed to compensate for the large charging capacity. [Pg.318]

The charging capacity of the long cable and the inductance of the shunt reactors direcdy connected to the cable are expressed as C and L, respectively. [Pg.319]

Most of the 500-/400-kV cables shown in Table 3.4 are installed in highly populated areas, hence the route lengths are limited to 10-20 km. These cables are equipped with shunt reactors for the compensation of the charging capacity, but their unit size and the total capacity are not as large due to the shorter route lengths. For these cables, only studies such as the reactive power compensation, the design of the cable itself, and the laying method are discussed in the literature. Transient studies on these cables are not available. [Pg.319]

During the planning stage, transmission capacity and reactive power compensation are normally studied. These studies mainly determine the cable route, the voltage level, the conductor size, and the amount and locations of shunt reactors. [Pg.320]

When the transmission development plan is designed for the cable, the cable route will be studied further. One characteristic of cables, compared to overhead lines, is that the laying of the cables and soil conditions of the location affect planning studies in addition to the land availability. These factors affect the burial depth, soil thermal resistivity, and cable separation between phases, which may necessitate changes to the conductor size and the amount and locations of shunt reactors initially deter-mined in the planning studies. [Pg.321]

The amount of shunt reactors (that is, the compensation rate of a cable) is a key figure that has a major impact on the following studies. A compensation rate close to 100% is often preferred since it can eliminate the reactive power surplus created by the introduction of the cable. It also offers a preferable condition for the TOV but causes a severe condition for the zero-missing phenomenon. The negative effect on the zero-missing phenomenon is not a primary concern as there are countermeasures established for tackling this effect. [Pg.321]

Usually, shunt reactors for 500-/400-kV cables are directly connected to the cables in order to mitigate the TOV when one end of the cable is opened. Shunt reactors for other cables are... [Pg.321]

Energize the shunt reactor after the Causes higher steady-state overvoltage and... [Pg.323]

In Countermeasure (5), a resistance is connected in a series to shunt reactors when a cable line is energized. The resistance needs to be sized sufficiently for the DC component to decay fast enough. After the cable line is energized, the resistance is bypassed in order to reduce the losses. Considering the additional cost for the resistance, this countermeasure is more suited for HV cable lines than EHV cable lines. [Pg.323]

In Step 2, shunt reactors are tripped before the line breakers of healthy phases. It is necessary to trip the shunt reactors of only healthy phases. At this time, it is not necessary or recommended to trip shunt reactors of the faulted phase since the current through shunt reactor breakers of the faulted phase does not cross the zero point. [Pg.325]

It is recommended to trip at least half of the shunt reactors of healthy phases as shown in Figure 3.25 as the tripping will normally lower the compensation rate below 50%. The remaining shunt reactors will be useful in maintaining the charging current within the leading current interruption capability of the line breakers. [Pg.325]

In Step 3, it is possible to open the line breakers of the healthy phases. Figure 3.26 shows that the current in the healthy phases contains the AC component and crosses the zero point after tripping the shunt reactors. [Pg.326]

When the charging capacity of a long EHV cable line is not compensated by shunt reactors that are direcdy connected to the cable, the leading current interruption capability requires careful attention [30]. Considering the typical capacitance of 0.2 pF/km, the maximum line length for a 400-kV cable line is limited approximately below 26 km without shunt reactors directly connected to the cable. Here, it is assumed that the leading current is interrupted at one end, and the other end is opened before the interruption. [Pg.326]

Usually, long EHV cable lines are compensated by shunt reactors that are directly connected to the cable. When the compensation rate is high enough, the leading current interruption capability is not a concern. If sequential switching is applied to a cable line as a... [Pg.326]

If a shunt reactor is directly connected to a cable, the cable line is discharged through the shunt reactor when it is disconnected from the network. In this case, the time constant of the discharge process is determined by the quality factor (Q factor) of the shunt reactor. Since the Q factor is around 500 for EHV shunt reactors, the time constant of the discharge process is around 8 min. [Pg.327]

Shunt reactors for other cables are often connected to buses, as the area compensation is applied at these voltage levels. When shunt reactors are connected to buses, the zero-missing phenomenon does not occur. In this case, however, the inductive VT connected to the cable needs to have enough discharge capability, and the line breaker needs to have sufficient leading current interruption capability. [Pg.278]

Figure 3.23 shows an example of current waveforms when an EHV cable is energized with its shunt reactors. It can be seen that the ac component of the energization current is very small since the compensation rate is close to 100%. The simulation was run for 0.2 s, but the energization current did not cross the zero point during this duration. Since the Zero-missing phenomenon is caused by a dc component of an energization current, it is most severe... [Pg.278]


See other pages where Shunt reactors is mentioned: [Pg.557]    [Pg.845]    [Pg.850]    [Pg.432]    [Pg.320]    [Pg.1520]    [Pg.202]    [Pg.317]    [Pg.318]    [Pg.322]    [Pg.322]    [Pg.322]    [Pg.323]    [Pg.327]    [Pg.327]    [Pg.187]    [Pg.272]    [Pg.273]    [Pg.273]    [Pg.275]    [Pg.278]    [Pg.280]   
See also in sourсe #XX -- [ Pg.850 ]




SEARCH



Shunt

© 2024 chempedia.info