Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Equipment support blocks

We will concentrate in the following on the design of foundations and equipment support blocks, since these are the civil items which are the most closely integrated with the overall plant design. Foundation design follows at its upper end from the plant layout and the loads and details of supported equipment and steelwork, and at the lower end from the design criteria produced by the geophysical consultant. [Pg.231]

Test Methods. There is no standard test method for measuring transmissibihty or isolation efficiency of vibration isolation devices. The most common procedure is to measure the vibration transmitted to the supporting stmcture with the isolators in place and with the equipment supported on rigid blocking. From these measurements the insertion loss in dB is deterrnined by the following where T is the transmitted vibration with isolators in place and is the transmitted vibration with rigid supports. [Pg.319]

Pieces of polypropylene saddles defmned at tenqioatuies of about 250T and passed through the support screen. Pieces were found in downstream equipment and blocked booster pump suction. When the still was opened, only 1 ft of the original 20 ft was found. Despite the loss, the amine was adequately regenerated. Repacking with ceramic saddles solved problem. [Pg.742]

The BSD can either shut down the entire facility, or it can be designed for two levels of shutdown. The first level shuts down equipment such as compressors, lean oil pumps, and direct fired heaters, and either shuts in the process or diverts flow around the process by closing inlet/outlet block valves and opening bypass valves. The second level shuts down the remaining utilities and support facilities, including generators and electrical feeds. [Pg.405]

Careless Workmanship. One laboratory operator combined a variety of equipment for a distillation procedure and finally came up with something that met his needs. In other words, it worked —but he had a tangle of wires, water hoses, and blocks of scrap wood for support. With less than one day s additional work, he could have improved both performance and safety features. [Pg.137]

Chromatographic system. The gas chromatograph is equipped with a flamioniza-tion detector and a 2 mm x 1.8 m glass column packed with 10% phase G34 on 80- to 100-mesh support SI A. The column temperature is maintained at about 150 °C, and the injection port and the detector block temperatures are maintained at about 250 °C. Dry helium is used as the carrier gas at a flow rate of about 40 mL/min. Chromatograph the Standard preparation, measure the peak responses, and calculate the ratio, Rs, as directed for procedure the relative retention times are about 0.5 for valproic acid and 1.0 for biphenyl the resolution, R, between valproic acid and biphenyl is not less than 3.0 the relative standard deviation for replicate injections is not more than 2.0%. [Pg.227]

Chromatographic System (See Chromatography, Appendix IIA.) Use a gas chromatograph equipped with a flame-ionization detector, and containing a 2.4-m x 4-mm (id) boro-silicate glass column, or equivalent, packed with 2% liquid phase, 5% phenyl methyl silicone on 80- to 100-mesh support (Supelcoport, or equivalent). Maintain the column isother-mally at a temperature between 270° and 280°, and the injection port and detector block at about 310°. Use helium as the carrier gas at a flow rate of about 70 mL/min. [Pg.204]

As shown, the construction of the bed is such that the layers are supported by an underdrain mechanism. This support may simply be a perforated plate or septum. The perforations allow the filtered water to pass through. The support may also be made of blocks equipped with holes. The condition of the bed is such that the coarser heavy grains are at the bottom. Thus, the size of these holes and the size of the perforations of the septum must not allow the largest grains of the bed to pass through. [Pg.344]

For the actual run, stock solutions of common reagents and building blocks must be prepared, and the solid support or solid-supported reagents dispensed into the appropriate reaction vessels (rvs). The reactions must be set up under the proper conditions, run, and subsequently worked up in an appropriate manner. This is followed by optional purification steps and, finally, isolation of the product For all of these steps, equipment is available that helps to achieve high throughput... [Pg.519]

Other systems or equipment which support normal operations or normal shutdown are not available (Example feed, product, or cooling medium flow may be lost because of equipment failure or because pipes are plugged or blocked)... [Pg.82]

The main cause of deactivation are elements or compounds which chemically attack the catalytically active material or its support. Also, structural changes and pore blocking are important issues of deactivation. A variety of poison compounds containing elements such as halogens, alkah metals, alkaline earth metals, arsenic, lead, phosphorus, and sulfur are mentioned in the hterature. AS2O3 is the most severe poison in coal-fired power plant operation in Germany. In power plants equipped with wet-bottom boilers alkah metal oxides mostly remain in the molten ash, whereas AS2O3 tends to escape into the flue gas and deposits on the catalyst. [Pg.148]


See other pages where Equipment support blocks is mentioned: [Pg.167]    [Pg.318]    [Pg.318]    [Pg.38]    [Pg.348]    [Pg.471]    [Pg.420]    [Pg.380]    [Pg.1359]    [Pg.255]    [Pg.337]    [Pg.175]    [Pg.105]    [Pg.1359]    [Pg.358]    [Pg.337]    [Pg.338]    [Pg.350]    [Pg.348]    [Pg.471]    [Pg.428]    [Pg.205]    [Pg.206]    [Pg.261]    [Pg.206]    [Pg.172]    [Pg.100]    [Pg.2903]    [Pg.178]    [Pg.216]    [Pg.4]    [Pg.1359]    [Pg.522]    [Pg.117]    [Pg.19]    [Pg.226]    [Pg.191]   
See also in sourсe #XX -- [ Pg.231 ]




SEARCH



Equipment support

Support blocks

© 2024 chempedia.info