Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Earliest due date

For problems that are solvable in polynomial time, it is usually relatively easy to find efficient algorithms. For the simplest of these problems, a simple sort is all that is required. For example, it may only be necessary to order the jobs in increasing order of their due dates (the so-called earliest due date rule [EDD]) or in decreasing order of the Wjlpj ratios (the so-called weighted shortest processing time [WSPT] first rule. For more complicated polynomial time problems, more sophisticated techniques such as dynamic programming are required. [Pg.1722]

The earliest due date nde, which schedides the jobs in increasing order of their due dates, minimizes the maximum lateness on a single machine (see Jackson 1955), that is, l f , , as well as in a proportionate flow shop, that is, Fm py = pj L. However, it does not provide an optimal solution for other due date-related problems, such as l 27j. Instances of l 27j with... [Pg.1723]

EAM, see Enterprise asset management Earliest due date rule (EDD), 1722-1724 EA3, 2563... [Pg.2724]

Once we have a job sequence, the optimal schedule including ET can be obtained by the algorithm INSERTJDLE proposed in the previous section. On the other hand, the sequencing problem with the sequence-dependent setup times is well known as an NP-hard problem, and then, an optimal sequence for the problem cannot be found in a reasonable computation time. In this section, to find a good solution for the problem, we propose a number of heuristic procedures, each of which includes the INSERTJDLE algorithm for assigning idle times between jobs. The first one is using the well-known heuristic rule EDD (earliest due date), and the procedure is as follows ... [Pg.271]

In the earlier proposed two heuristics (EDD and MS), a job is attached after the last job of current partial sequence when it is selected by the corresponding rule (due date, slack time, or objective value). They are simple to make solutions but the performances of the solutions are not likely to be very good. So we propose another heuristic, mEDD algorithm, in which a job is selected by the earliest due-date rule and it is not attached after the last job of the current sequence but inserted into a proper position between jobs in the current sequence. Though the calculation quantity of the algorithm increases, we can anticipate better performance from the algorithm. The detailed procedure is as follows ... [Pg.273]

These two sets S and C are not the only important characteristics of the fixed cycle. The service discipline is also very important. During the production interval of a type we can only woik on orders of that type. The orders of that type will be produced according to the FCFS-rule. Because of the exact due dates this rule is the same rule as the earliest-due-date rule (FDD). If there are no (more) orders of a type we have to wait for new orders of this type or for the end of the production interval. This way of service, in which we stop working on orders from a certain type at the end of a production interval, is usually called gating service. We will consider two different ways of gating service. [Pg.22]

The capacity will be allocated to one or more types of products in several steps. Hrst we detmnine which of the types is the most important type, of course with a sufficient number of penalty points. If the number of orders for this most important type is less than or equal to the available capacity, then all the orders for this type will be produced. If not, then we will start with the orders with the earliest due date and if orders have the same due date we will start with the orders with the highest priority. The allocation of the capacity stops if all the normal available capacity has been allocated and if the number of periods until the due dates of the remaining orders is larger than some priority-dependent constant. If there are remaining orders for which the number of periods until the due date is not larger than this priority-dependent constant, then extra capacity will be used to produce these orders. In Example 7.1. we will consider orders with two different priorities normal and urgent orders. For the normal orders we will use extra capacity for all orders with a residual lead time that is less than or equal to one period. For the urgent orders we will use extra capacity for all orders with a residual lead time that is less than or equal to two periods. [Pg.140]

Some BOMs have validities start and end of validity interval and the reference time used to determine if the product flow is valid or not earliest start, due date, start or end of production. [Pg.81]

The due date calculated by backwards termination is a minimum over all latest ends of production for every successor quant. Therefore it is exact for quants with at most one successor. If there are two or more successors the delay costs calculated with the due date may be higher than the real delay costs because the due date is the smallest end necessary to supply the earliest successor. [Pg.82]

Thus, we can try to prevent these drug disasters to the maximum extent possible, we can try to identify and diagnose them at the earliest possible date (and so minimize the number of patients hurt or disadvantaged), but, in the present state of scientific knowledge, we cannot eliminate drug withdrawals due to unexpected toxicity. [Pg.580]

One of the earliest papers that studies DDM is by Conway [27]. He considers four due date policies, CON, NOP, TWK and RND, and tests the performance of nine priority dispatching rules for each of these policies in a job shop. For the objective of minimizing average tardiness, the author finds that under FCFS sequencing, the four due date policies exhibit similar, mediocre... [Pg.507]

In contrast to enamines1,2, the chemistry of 1,1-enediamines have been only briefly studied although the earliest reports3,4 of such compounds may date back to the 1940s. This has been partly due to the relative difficulty of the synthesis of simple 1,1-enediamines 1 in earlier years. A convenient method for the preparation of conjugated... [Pg.1304]

Another example of the case study approach used in the course involves the evolution of scientific ideas regarding matter. As far as we know, the earliest concept of an atom dates to Democritus of ancient Greece. His philosophical reasoning led him to conclude that there must be a smallest un-cuttable (a-tom) piece of any given substance. At the start of the 19 century, no one had any defensible ideas about the structure of matter or how elements combine to make compounds. The theory that answered these questions came from John Dalton. He reasoned that if only certain specific ratios of substances combine, it must be due to fundamental units of matter, the atoms, which combine in that same ratio. Some of his original concepts were modified by subsequent scientists to account for new observations, but his basic idea led to numerous discoveries that provided a better understanding of the nature of matter. [Pg.338]

Scotland (Quye, 1993). Instability of the earliest plastics, cellulose nitrate and acetate, is expected due to their poorly stabilized and largely experimental formulations and because they are the oldest man-made plastics in museums dating from the late nineteenth and early twentieth centuries. However, PVC and polyurethanes were first commercially available after World War II and are still used, so their short lifetimes are more difficult to understand. Until the late 1970s, plastics were widely believed to last forever and to be almost indestructible, a belief fuelled by the plastics industry s claims for the durability of their products (Morgan, 1994). [Pg.10]


See other pages where Earliest due date is mentioned: [Pg.1722]    [Pg.2724]    [Pg.497]    [Pg.541]    [Pg.1722]    [Pg.2724]    [Pg.497]    [Pg.541]    [Pg.437]    [Pg.329]    [Pg.46]    [Pg.69]    [Pg.478]    [Pg.497]    [Pg.521]    [Pg.529]    [Pg.542]    [Pg.181]    [Pg.219]    [Pg.127]    [Pg.374]    [Pg.127]    [Pg.406]    [Pg.118]    [Pg.222]    [Pg.186]    [Pg.267]    [Pg.406]    [Pg.463]    [Pg.349]    [Pg.2643]    [Pg.710]    [Pg.215]    [Pg.280]    [Pg.138]    [Pg.114]    [Pg.203]    [Pg.23]    [Pg.161]   
See also in sourсe #XX -- [ Pg.497 ]




SEARCH



Due dates

© 2024 chempedia.info