Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Due date

On the due date when the tenders should have been received, record those that have been submitted and discard any submitted after the deadline. Conduct an evaluation to determine the winner - the subcontractor that can meet all your requirements (including confidence) for the lowest price. The evaluation phase should involve all your staff that were involved with the specification of requirements. You need to develop scoring criteria so that the result is based on objective evidence of compliance. [Pg.319]

Don t wait until the due date for the completion of the action to check if work has started. [Pg.472]

At this point the lower-bounding scheme consists of solving a single machine scheduling problem where for each job i, the release time is the due date is, and the processing time is This nonbottleneck scheme can be further simplified in two steps. First, we can assume that for a/8 =. ., avoiding the need to consider release times of and due dates of, which turns an NP-complete problem, into one solvable in polynomial time. If only one of these were to be relaxed, the schedule can still be foimd in polynomial time by Jackson s rule (Jackson, 1955). Second, we can avoid the computation of completely, by assuming that the maximum is obtained at / = m for all values of i. [Pg.290]

Determine trimesters and a due date for a pregnancy based on the last menstrual period. [Pg.721]

Due dates typically are estimated at 40 weeks gestation however, infants delivered at between 38 and 42 weeks are considered full term. [Pg.724]

Bonds are promissory notes that can be issued by corporations or governmental bodies. They are contracts in which the seller agrees to pay the owner the face value (called par value) of the bond at a certain date (maturity or due date) and a given amount of interest at various stated times. Bonds can be sold to individuals, but... [Pg.318]

A certain power company gives a ly% discount if a customer pays the bill at least ten days before the due date. If Inez pays her 48.50 bill ten days early, how much money will she save, rounded to the nearest cent ... [Pg.87]

In many cases a start solution (as shown in Figure 4.3) already exists or is easy to obtain. The most common target is the due date where we distinguish between the... [Pg.66]

Delay costs arise in case the product cannot be produced to meet a certain deadline. In order to determine these the value specified for each product is multiplied with the amount of days which the product has been produced late (example delay costs = 100 Euro, production ends four days after the due date — 400 Euro delay costs arise). [Pg.72]

Some BOMs have validities start and end of validity interval and the reference time used to determine if the product flow is valid or not earliest start, due date, start or end of production. [Pg.81]

The first way to calculate the delay and stock costs of a quant is to multiply a delay cost factor/stock cost factor with the difference between the due date and the end of production or any time of the quant. In general this is a rough approximation for an easy and fast calculation. [Pg.82]

The due date calculated by backwards termination is a minimum over all latest ends of production for every successor quant. Therefore it is exact for quants with at most one successor. If there are two or more successors the delay costs calculated with the due date may be higher than the real delay costs because the due date is the smallest end necessary to supply the earliest successor. [Pg.82]

In the beginning there is a general loop to decide if more lot sizing procedures should be applied to the existing quant network to meet the constraint of the minimum batch sizes of products. Then the quant network is examined, free usable stocks and free quantities of quants are made available. The material balances of any quant are calculated and decisions are taken whether quants require further explosions of their BOM. Structures for a fast cycle checking, sorting of existing quants and quant links and forecast intervals are built up. A recalculation of the due dates for all quants - also the ones of orders - can be done if specified by the user. [Pg.84]

Typically, orders are simpler to explode than anonymous demands, because for an anonymous demand it might be required to define a distribution of the forecast quantities over the forecast interval only one quant, quants with equal quantities, due dates at the beginning or end or equally distributed. At this time it can be defined for each product if lot sizes, batch sizes, minimum quantities, maximum quantities of quants should be considered. The quantities are broken into predefined equal parts and then assembled until they meet the mentioned constraints. [Pg.84]

Fig, 4.17 Static lot sizing for a batch product. The plan is a just-in-time production. According to the due date every batch is planned with minimum costs. Setups are indicated with a red arrow to the right. The stock costs of 45,216 Euro are a result of the different batch sizes of the product itself and its successor product. Therefore not every batch can be planned just-in-time. The changeover costs are 4,182,935 Euro. The sum of both costs is 4,228,151 Euro. The lower part of Figure 4.17 shows the result of... [Pg.87]

During normal operation of the copper plant, there are a number of regular maintenance jobs that need to be planned. They are included in the scheduling problem as additional jobs that have given release dates and due dates. These maintenance jobs can mostly be performed only when a unit is empty and not in use. The optimization approach finds the best location for each maintenance job with the least impact on production throughput and, furthermore, modifies the batch recipes such that there will be a suitable break in the operation for the equipment that must be maintained. [Pg.104]

The decisions should be taken in an optimal fashion subject to the plant topology and the processing constraints with the objective to maximize the profit, given as the difference of revenues for products and costs for the production. The demands are specified by their amounts and their due dates, where the revenues decrease with increasing lateness of the demand satisfaction. The production costs consist of fixed costs for each batch and for the start-up- and shut-down-procedures of the finishing lines, and variable costs for the product inventory. [Pg.141]

Demand patterns Multiple product demands appear which are specified by their amounts and their due dates. [Pg.143]

The objective to be minimized is a weighted sum of deviations of the produced amounts from the demanded amounts d at the due dates im. Overproduction and underproduction, i.e., positive differences — d% and d — p respectively, are weighted by the nonnegative factors am and fim. If the value of the objective function is represented by z e R the objective can be stated as follows ... [Pg.152]

Subsets of products Timings of polymerization starts Due dates... [Pg.160]

Demand patterns can also vary significantly ranging from cases where due dates must be obeyed to cases where production targets must be met over a time horizon (fixed or minimum). Changeovers are also a very important factor, which is particularly critical in cases of transitions that are sequence dependent on the products, as opposed to simple setups that are only unit dependent. [Pg.166]

We can then conclude that while the discrete time STN and RTN models are quite general and effective in monitoring the level of limited resources at the fixed times, their major weakness in terms of capability is the handling of relatively small processing and changeover times. Regarding the objective function, these models can easily handle profit maximization (cost minimization) for a fixed time horizon. Intermediate due dates can be easily modeled. Other objectives such as makespan minimization are more complex to implement since the time horizon and, in consequence, the number of time intervals, are unknown a priori (see [11]). [Pg.174]

We can conclude that the continuous-time STN and RTN models based on the definition of global time points are quite general. They are capable of easily accommodating a variety of objective functions such as profit maximization or makespan minimization. However, events taking place during the time horizon such as multiple due dates and raw material receptions are more complex to implement given that the exact position of the time points is unknown. [Pg.175]

Mendez, C.A., Henning, G.P. and Cerda, J. (2000) Optimal scheduling of batch plants satisfying multiple product orders with different due-dates. Comput. Chem. Eng., 24, 2223-2245. [Pg.184]

The market demand must be satisfied. This means that the demanded quantities of the final products S3 and S4 must be present in the storage tanks when they have to be delivered to the customer. Such due dates or deadlines define timing constraints for the end of the production. Missing a due date often causes a penalty (or the customer pays less to the plant operator). Missing a deadline is not allowed here the customer must be satisfied before the deadline expires. [Pg.217]


See other pages where Due date is mentioned: [Pg.455]    [Pg.403]    [Pg.416]    [Pg.473]    [Pg.473]    [Pg.473]    [Pg.473]    [Pg.508]    [Pg.14]    [Pg.237]    [Pg.67]    [Pg.67]    [Pg.80]    [Pg.132]    [Pg.144]    [Pg.144]    [Pg.145]    [Pg.150]    [Pg.150]    [Pg.155]    [Pg.155]    [Pg.157]    [Pg.165]    [Pg.207]    [Pg.218]    [Pg.251]   
See also in sourсe #XX -- [ Pg.217 ]




SEARCH



Common due date

Due date management

Due date tightness

Earliest due date

Operation due dates

© 2024 chempedia.info