Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Stock costs

Fewer parts means improved reliability, fewer stock costs, fewer invoices from fewer suppliers and possibly fewer quality problems... [Pg.306]

The first way to calculate the delay and stock costs of a quant is to multiply a delay cost factor/stock cost factor with the difference between the due date and the end of production or any time of the quant. In general this is a rough approximation for an easy and fast calculation. [Pg.82]

This more detailed model is necessary for target stock calculations where productions may overlap, the lengths of quants differ significantly and quants have multiple predecessors and successors (see Figure 4.14). Calculating lot sizes with for example the formula of Andler yields completely different results and the sum of changeover costs and stock costs are much higher. [Pg.82]

The planner can indude the stock costs in addition to the other costs, but as a consequence delay costs are balanced with stock costs. Here this effect is not wanted at first high demand satisfaction is required. Keeping this to the maximum level, stock costs are lowered around this optimum. The trade off between production for future demands and inventory costs can be maximized by the so called shift operator. [Pg.82]

The objective function of this scenario contains changeover costs, dday costs, stock costs and production costs. The delay costs and stock costs can be calculated in different ways dependent on the situation in which they are needed. [Pg.82]

The static lot sizing has several positive aspects. Big quant networks are transformed into smaller ones thus making faster calculations possible still fulfilling all constraints. The objective function can be reduced to contain only the changeover costs and the stock costs with the aim to find a trade off between these two costs (see Figure 4.17). [Pg.85]

Fig. 4.16 The examination of combining 236 of a total of 28770 quants (253 quants are visible). Change over costs are Euro 11.2 m. in the upper part, the stock costs are 235,000 Euro. When combining the selected quants the stock and delay costs are reduced to 45,000 Euro + Euro 4 m. for changeover. Fig. 4.16 The examination of combining 236 of a total of 28770 quants (253 quants are visible). Change over costs are Euro 11.2 m. in the upper part, the stock costs are 235,000 Euro. When combining the selected quants the stock and delay costs are reduced to 45,000 Euro + Euro 4 m. for changeover.
At the end of an optimization operator a feasible solution has been built up. Further application of algorithms should improve this plan. Therefore the parts with the most promising potential for improvement must be found. Costs are mostly not a good criterion because they change in a non continuous way quants change from delay to stock costs, changeover costs are zero or non-zero. Also a shift model introduces a lot of volatility. [Pg.86]

Fig, 4.17 Static lot sizing for a batch product. The plan is a just-in-time production. According to the due date every batch is planned with minimum costs. Setups are indicated with a red arrow to the right. The stock costs of 45,216 Euro are a result of the different batch sizes of the product itself and its successor product. Therefore not every batch can be planned just-in-time. The changeover costs are 4,182,935 Euro. The sum of both costs is 4,228,151 Euro. The lower part of Figure 4.17 shows the result of... [Pg.87]

Debits Stock cost Naphtha Extra, butanes Direct operating cost Total process costs Ethylizing Taxes and insurance Royalties... [Pg.58]

Using the accelerated capital recovery system (ACRS) still showed negative cash flows for each project. The reason for these negative cash flows is that tire pyrolysis is only economic with unique situational variables. There are a number of questions about product quality, product price, and feed stock cost which tend to lend a vagueness to the economic analysis..."... [Pg.312]

Increased feed stock costs require higher ethylene yields and better selectivity. [Pg.158]

After start-up, the furnace effluent was analyzed and showed an increase in ethylene yield of 0.9 wt % whereas the PFO decreased by 1.2 wt %. These yield improvements resulted in a considerable decrease of net feed stock costs. [Pg.176]

It mi t be possible to close an ammunition depot and a small technical stores department. Capital saving on Works Services is estimated at ,. 3 million. Savings on ammunition stocking costs would amount to 28 million. New purchases will be reduced from 20 million to 17 million per annum. ... [Pg.88]

For supply chains, transportation flows enable products or components to change location, thus enabling them to be used at their demand points. The timing of these transportation flows in turn interacts with transport capacity and chain structure to impact supply chain performance. Given this interaction, the total supply chain impact of a choice of transportation flows has to include transport costs, cycle stock costs, safety-stock costs, and in-transit inventory costs. For each possible transport mode, there are... [Pg.21]

Safety stock costs If the demand time, the transit time, or both are uncertain, it may be necessary to carry inventory as a buffer against demand uncertainty. As discussed earlier, the extent of this inventory buffer depends on the magnitude of the demand uncertainty during the supply lead time and the planned in-stock service level. If the planned in-stock probability is expressed as service and the demand over lead time has a standard deviation of ct i, then the safety stock level is expressed as (Note that we assume that... [Pg.33]

Cycle Stock Costs Given the full truckload shipments, the size of the deliveries of each component received by each assembly plant is 3,000 units. In the absence of demand uncertainty at each plant, the next truck delivery would be scheduled when the components in this delivery are consumed. This means that the inventory level cycles between 3,000 and 0 units. The average inventory is thus the average height of a right triangle whose height is 3,000 units 3,000... [Pg.35]

The associated cycle stock cost = 750 X 0.4 = 300/day Chicago (component 2) ... [Pg.43]

M Clark M, Changing pressure redistributing mattress stocks costs and outcomes . BrJNurs, 2005 14 (Stqrpl) 30-32. [Pg.508]

The costs of a wire harness representing the contract with the supplier. The contract defines all involved costs like production cost, stock costs, transportation costs and price deductions. [Pg.512]

Demand response capability must ensure customer satisfaction and increase supplier s profit. Companies must first convert independent demand of products to determine the dependent demand for location-specific products. Failing to convert demand to each location may lead to over or under stocking cost (see Tesco s problem below). It may also incur unnecessary shipping expenses. Dependent demand focuses on demand at each location, demand in the factory, demand for specific parts for the suppliers, and the demand for logistics within the entire network. [Pg.37]

Figure 5.1 A comparison of energy-related and non-energy-related costs (excluding feed-stock costs) for a typical U.S. petrochemical plant, including the effect of energy conservation. (Information from Kenney, p.3.)... Figure 5.1 A comparison of energy-related and non-energy-related costs (excluding feed-stock costs) for a typical U.S. petrochemical plant, including the effect of energy conservation. (Information from Kenney, p.3.)...

See other pages where Stock costs is mentioned: [Pg.166]    [Pg.65]    [Pg.82]    [Pg.87]    [Pg.478]    [Pg.174]    [Pg.159]    [Pg.427]    [Pg.52]    [Pg.79]    [Pg.7]    [Pg.8]    [Pg.10]    [Pg.10]    [Pg.40]    [Pg.42]    [Pg.43]    [Pg.140]    [Pg.141]    [Pg.574]    [Pg.159]    [Pg.27]   
See also in sourсe #XX -- [ Pg.82 ]




SEARCH



Cycle stock costs

Cycle stock costs transportation

Safety stock costs

Safety stock costs transportation

Stock-out cost

© 2024 chempedia.info