Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Startup flow

Startup flow to the expander is designed to be supplied from the discharge of the compressor through a throttle valve and cooler. A careful study of the characteristics of the compressor blow-off valve and the expander startup valve was performed by Solvay process engineers. Based on these calculations, the startup cooler and valve were sized to supply the minimum required flow to tlie expander wheel. [Pg.456]

Fig. 19. a Predicted startup-flow in extension and shear for the constitutive equation derived for a pom-pom polymer with q=5. Stress divided by the strain-rate is plotted (so that early time response is rate-independent) against time after initiation of the flow for a range of dimensionless rates from 0.001 to 3. Both axes are logarithmic... [Pg.248]

Fig. 19. b Experimental results in startup flow in shear and extension on branched LDPE from Meissner [3]. The qualitative nature of the response in the two flows is remarkably similar to the pom-pom model in (a)... [Pg.249]

Mathematically speaking, a process simulation model consists of a set of variables (stream flows, stream conditions and compositions, conditions of process equipment, etc) that can be equalities and inequalities. Simulation of steady-state processes assume that the values of all the variables are independent of time a mathematical model results in a set of algebraic equations. If, on the other hand, many of the variables were to be time dependent (m the case of simulation of batch processes, shutdowns and startups of plants, dynamic response to disturbances in a plant, etc), then the mathematical model would consist of a set of differential equations or a mixed set of differential and algebraic equations. [Pg.80]

Consideration of the cash-flow stages in Fig. 9-10 shows the factors that can affecd the (EMIP) and (IRP). if the reqiiired capital investment is increased, it is necessary to increase the rate of income after startup for the (EMIP) to remain the same. In order to have the (EMIP) small, it is necessary to keep the research and development, design, and construction stages short. [Pg.813]

Here, p is the number of payback periods that have elapsed since the project started to generate positive net annual cash flows Acp up to any given year n since project startup. It is given by... [Pg.835]

It is also possible to combine (MSF) considerations with evaluation of the true discounted-cash-flow rate of return (DCFRR) by using Eq. (9-62). The relationship of Eq. (9-59) is independent of inflation if all money values are based on those prevailing in the startup year. For this case, Fig. 9-34 shows the true (DCFRR) reached in a given time, expressed as the number of elapsed payback periods for various values of the payback period. [Pg.835]

Other advantages of gravity beds include flexibility in gas and sohds flow rates and capacities, variable retention times from minutes to several hours, space economy, ease of startup and shutdown, the potentially large number of contacting stages, and ease of control by using the inlet- and exit-gas temperatures. [Pg.1220]

Much of the basic theory of reaction kinetics presented in Sec. 7 of this Handbook deals with homogeneous reaclions in batch and continuous equipment, and that material will not be repeated here. Material and energy balances and sizing procedures are developed for batch operations in ideal stirred tanks—during startup, continuation, and shutdown—and for continuous operation in ideal stirred tank batteries and plug flow tubulars and towers. [Pg.2098]

During filling, the catalyst is distributed uniformly to avoid the possibility of channeling that coiild lead to poor heat transfer, poor conversion, and harm to the catalyst because of hot spots. During startup, sudden surges of flow may disturb the bed and are to be avoided. For instance, in a study of a hydrodesulfuiizer by Murphree et al. (Ind. Eng. Chem. Proc. Des. size unit varied between 47 and 80 percent with different modes of loading and startup. [Pg.2102]

Startup and Overcapacity From a design standpoint and also operationally, it is important to remember that pump-turbines not only do not generate power before they attain about 40 percent of design flow but actually consume power in decreasing amounts as the flow is increased from zero to 40 percent. This means that they should... [Pg.2531]

Some toll processes lend themselves to test runs in the pre-startup phase. Actual materials for the toll may be used in the test or substitute materials, typically with low hazard potential, are often used to simulate the charging, reaction, and physical changes to be accomplished in the toll. Flow control, temperature control, pressure control, mixing and transferring efficiency can be measured. Mechanical integrity can be verified in regard to pumps, seals, vessels, heat exchangers, and safety devices. [Pg.103]

The required suction pressure to the expander is not available until the oxidizer tower reaches design pressure. With two compressors in operation this takes approximately 15 min. Since the expander wheel is mounted on the compressor pinion, enough flow must be available at startup to prevent overheating. The calculated windage loss of the expander wheel (40 hp) requires about 16,000 Ib/lir of flow to prevent overheating. [Pg.456]

Column Bottom Temperature. The bottom temperature is often controlled on the reboiler outlet line with a control valve in the heating medium line. The control point can also be on a bottom section tray. Care must be exercised in location of the temperature control point. It is recommended, especially for large columns, that a cascade arrangement be used. The recommended scheme has a complete flow recorder/controller (FRC) in the heating medium line including orifice and control valve. The set point of this FRC is manipulated by the temperature recorder/controller (TRC). This eliminates the TRC from manipulating the control valve directly (recall that temperature is the most difficult parameter to control). This makes for smoother control for normal operations. Also, it is handy for startup to be able to uncouple the TRC and run the reboiler on FRC for a period. [Pg.68]

The first circuit that can burn up a significant amount of power is the startup circuit. Here dc current is taken from the input voltage so that the control IC and driver circuits have enough power to start the power supply. If the type of start-up circuit does not cutoff its current flow after a successful start-up has been done, then up to 3 W can be continuously dissipated within the circuit depending upon the input voltage. [Pg.139]


See other pages where Startup flow is mentioned: [Pg.226]    [Pg.109]    [Pg.10]    [Pg.201]    [Pg.226]    [Pg.226]    [Pg.109]    [Pg.682]    [Pg.1906]    [Pg.426]    [Pg.469]    [Pg.226]    [Pg.109]    [Pg.10]    [Pg.201]    [Pg.226]    [Pg.226]    [Pg.109]    [Pg.682]    [Pg.1906]    [Pg.426]    [Pg.469]    [Pg.265]    [Pg.146]    [Pg.295]    [Pg.378]    [Pg.631]    [Pg.808]    [Pg.811]    [Pg.874]    [Pg.875]    [Pg.1564]    [Pg.2039]    [Pg.2187]    [Pg.2225]    [Pg.2226]    [Pg.2517]    [Pg.116]    [Pg.216]    [Pg.399]    [Pg.460]    [Pg.475]    [Pg.167]    [Pg.536]    [Pg.126]    [Pg.78]   


SEARCH



Startup

© 2024 chempedia.info