Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Floors/flooring requirement considerations

Figure 9 shows the details of a typical horizontal tube-type ozone generator. This unit is preferred for larger systems. Water-cooled plate units are often used in smaller operations. However, these require considerably more floor space per unit of output than the tube-type units. The air-cooled Lowther plate type is a relatively new design. It has the potential for simplifying the use of ozone-generating equipment. However, it has had only limited operating experience in water treatment facilities. [Pg.492]

They do require extensive floor space, however, and this can be a disadvantage if many stages are needed. Also, mixer-settlers generally have Iaige residence times and therefore require considerable time to achieve steady state and large liquid-liquid inventories, Another di rad vantage of mixer-settlers is that most commercial units are difficult to seal, If the main purpose of the extraction step is to dehydrate an organic material, this feature can preclnde their use. [Pg.441]

It is a sophisticated instrument requiring the services of a professional and the technique is a relatively slow one. Barring any difficulty, about ten oil samples a day can be analyzed. The instrument is expensive, costing about 120,000 and requiring considerable floor space. [Pg.83]

Columns are useful for processing low flow rates and for systems that exhibit a tendency to form emulsions. An important benefit of a column contactor is the large number of possible theoretical stages and the ability to operate closer to the operating line rather than the equilibrium curve, thereby maximising mass-transfer kinetics. The settling volume is considerably lower than for the corresponding mixer-settler, so columns are preferred for systems in which solution lock-up and low solvent inventories are important (such as in precious metal extraction systems). Columns take up very little floor space, but require considerable headroom mixer-settler requirements are the opposite (Movsowitz et al. 2001 Fox et al. 1998). [Pg.180]

The specification, selection, layout, maintenance, and operation of plant equipment can influence plant noise levels and employee noise exposures. Each of these items is worth considering when evaluating noise control requirements and available options. For those companies that are moving office workers out onto the factory floor, these considerations are essential. [Pg.426]

Cracking reactions are endothermic, 1.6—2.8 MJ/kg (700—1200 BTU/lb) of hydrocarbon converted, with heat supplied by firing fuel gas and/or fuel oil in side-wall or floor burners. Side-wall burners usually give uniform heat distribution, but the capacity of each burner is limited (0.1—1 MW) and hence 40 to 200 burners are required in a single furnace. With modem floor burners, also called hearth burners, uniform heat flux distribution can be obtained for coils as high as 10 m, and these are extensively used in newer designs. The capacity of these burners vary considerably (1—10 MW), and hence only a few burners are required. The selection of burners depends on the type of fuel (gas and/or liquid), source of combustion air (ambient, preheated, or gas turbine exhaust), and required NO levels. [Pg.436]

New types of anodes have been developed and tested as shown in Fig. 16-5 to improve the possibility of maintenance and repair. They can be lifted onto a ship and repaired. The connecting cables are also replaceable. In shallow water, the anchorage must be accurately calculated because considerable dynamic stressing can occur in heavy seas. The ocean floor must be suitable for long-term anchorage. No supply ships must anchor in the area around the platform. This requirement alone often prevents the installation of impressed current anodes since the operator does not wish or is not able to restrict himself to these conditions. [Pg.375]

CP-1 was assembled in an approximately spherical shape with the purest graphite in the center. About 6 tons of luanium metal fuel was used, in addition to approximately 40.5 tons of uranium oxide fuel. The lowest point of the reactor rested on the floor and the periphery was supported on a wooden structure. The whole pile was surrounded by a tent of mbberized balloon fabric so that neutron absorbing air could be evacuated. About 75 layers of 10.48-cm (4.125-in.) graphite bricks would have been required to complete the 790-cm diameter sphere. However, criticality was achieved at layer 56 without the need to evacuate the air, and assembly was discontinued at layer 57. The core then had an ellipsoidal cross section, with a polar radius of 209 cm and an equatorial radius of309 cm [20]. CP-1 was operated at low power (0.5 W) for several days. Fortuitously, it was found that the nuclear chain reaction could be controlled with cadmium strips which were inserted into the reactor to absorb neutrons and hence reduce the value of k to considerably less than 1. The pile was then disassembled and rebuilt at what is now the site of Argonne National Laboratory, U.S.A, with a concrete biological shield. Designated CP-2, the pile eventually reached a power level of 100 kW [22]. [Pg.437]

Where an under-slung condenser has been specified, the provision of a basement to the engine room offers the attraction of compactness at the expense of enhanced civil works, while alternatively, the specification of pannier condensers can obviate the need for a basement and will simplify the foundation design, but will considerably increase the floor area requirements. The condensing plant itself consists essentially of banks of tubes through which cooling water flows and around which exhausted steam from the turbine is condensed to form a vacuum. Such tubes have traditionally been made of brass, but where severe corrosion conditions exist, cupro-nickel is sometimes used. [Pg.203]

One should assume that at least 200 ps of equilibration+sampling will be required for any reliable simulation in explicit water solvent. Since each simulation should be run at least twice (or forwards and backwards) to ensure a reproducible result, this means a floor of 400 ps simulation time will be required. Note that 200 ps (400 ps) is a lower bound, and that many simulations will need to be run considerably longer. It is not unusual to run protein-based simulations for a nanosecond or more to achieve convergence. For a large (protein based) system, this requires a substantial investment of computer time on today s computers. [Pg.28]

Before considering which properties to measure and which methods to use it is essential to clearly identify the purpose of testing because the requirements for each of the purposes are different. This may be an obvious point, but failure to appreciate what purpose the results must satisfy easily leads to unfortunate choice of method and conditions. Also, lack of consideration of why another person is testing and what they need to get from their tests frequently leads to poor appreciation of the merits and limitations of a particular test and inhibits communication between, for example, the university researcher and the factory floor quality controller. [Pg.8]


See other pages where Floors/flooring requirement considerations is mentioned: [Pg.359]    [Pg.104]    [Pg.359]    [Pg.219]    [Pg.44]    [Pg.202]    [Pg.884]    [Pg.266]    [Pg.253]    [Pg.1053]    [Pg.472]    [Pg.1589]    [Pg.85]    [Pg.1040]    [Pg.308]    [Pg.132]    [Pg.268]    [Pg.215]    [Pg.673]    [Pg.1157]    [Pg.343]    [Pg.188]    [Pg.96]    [Pg.617]    [Pg.17]    [Pg.113]    [Pg.29]    [Pg.171]    [Pg.747]    [Pg.260]    [Pg.472]    [Pg.600]   
See also in sourсe #XX -- [ Pg.103 ]




SEARCH



Flooring

Floors/flooring

© 2024 chempedia.info