Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Second Order Complete Plan

Even though the second order orthogonal plan is not a rotatable plan (for instance see Eqs. (5.114) and (5.115)), the errors of the experimental responses (from the response surface) are smaller than those coming from the points computed by regression. It is possible to carry out a second order rotatable plan using the Box and Hunter [5.23, 5.27] observation which stipulates that the conditions to transform a sequential plan into a rotatable plan are concentrated in the dimensionless a value where a = for k 5 and a = for k 5 respectively. Simulta- [Pg.395]

Fork = 2 the values of a rotatable plarming matrix of the second order are given  [Pg.396]

As a consequence, the Pjj coefficients will be linked with other coefficients and with the Pq constant term. Moreover, to solve the problem of coefficients we must resolve the normal equation system by computing the inverse of the char- [Pg.397]

For this case of second order complete plan, the specificity of the matrix of the coefficients results in an assembly of relations directly giving the regression values of the coefficients. In this example, where the complete second order plan is based on a 2 CFE, these relations are written as follows  [Pg.397]

It should be mentioned that, in the calculation of parameter s represents the number of spheres circumscribed to the experimental centre plan, y is recognized as the radius of each i circumscribed sphere (see relation (5.115)) and n is the [Pg.398]


Another PE spectroscopic general topic of the decade 1990-2000 has been the attempt to complete a list of first and second order organosilicon substituent perturbation increments (Section III.C) for both a and n parent molecules. Quite often, as has been demonstrated over and over in the preceding chapters, they prove to be useful to the silicon chemist in the proper planning of his experiments. [Pg.208]

N gives the total number of experiments in the plan. When we use a complete second order plan, it is not necessary to have parallel trials to calculate the reproducibility variance, because it is estimated through the experiments carried out at the centre of the experimental plan. The model adequacy also has to be examined with the next procedure ... [Pg.398]

In the method of Latin squares, the experimental plan, given by the matrix of experiments, is a square table in which the first line contains the different levels of the first factor of the process whereas the levels for the second factor are given in the first column. The rest of the table contains capital letters from the Latin alphabet, which represent the order in which the experiments are carried out (example for pressure level Pj, four experiments for the temperature levels Tj, T2, T3, T4 occur in the following sequence A, B, C, A where A has been established as the first experiment, B as the second experiment, etc). The suffixes of these Latin capital letters introduce the different levels of the factors. Table 5.58 presents the schema of a plan of Latin squares. We can complete the description of this plan showing that the values of the process response can be written in each letter box once the experiment has been carried out. Indeed, we utilize three indexes for the theoretical utterance of a numerical value of the process response (v). For exam-... [Pg.437]

Polya [1], who has examined the nature of problem solving, has devised a similar procedure. He states, "First, we have to understand the problem we have to see clearly what is required. Second, we have to see how the various items are coimected, how the unknown is linked to the data, in order to obtain the idea of the solution, to make a plan. Third, we carry out our plan. Fourth, we look back at the completed solution, we review and discuss it."... [Pg.96]

There are at least two approaches for defining the order of the activities. The first is the "plan for success" approach in which as many activities as possible are conducted in parallel to provide the shortest time path to the Go/No-Go decisions (proof of mechanism/ proof of concept/ etc.) and to the project completion. The second approach is used when there are very scarce resources or when there is a low probability of project success. This second approach defers expensive activities until a proof of concept (POC) has been achieved for the project. Once the POC has been achieved/ then a plan-for-success-style development plan for the project will be developed and implemented. One can also stage the development of lower prioritized projects in a portfolio/ if resources are limited/ or if the risk is still high and the project needs to be managed more conservatively by the organization. [Pg.430]

Brazilian uranium resources are presently estimated in 300,000 metric tons and the estimate on the thorium resources is of the order of one million metric tons. The country has presently one reactor (PWR/626 MWe) in operation and a second one (PWR/1300 MWe) has recently received authorization for completion, which is planned for 1999. A third reactor (PWR/1300 MWe), originally planned to be constructed in the same site as the other two is still awaiting for a government decision. [Pg.7]

On the day of attack, 15 September 1944, the elaborate plan for using the flame tractors completely broke down. The ist Marine Regiment was stopped by stiff resistance just beyond the beach, and its flame tractor waited five hours for some kind of order. The flame vehicles with the other regiments were told to stand offshore out of danger. When the three flame tractors eventually landed they stood idle on the beaches, a result no doubt of extreme confusion and the unfamiliarity of the marines with the weapon. Inactivity on the second day was caused by the fact that the air compressor had not yet landed. The flame vehicles saw action on the third day, and from then on their commitment was regular. ... [Pg.566]

CMPP is made up of four basic subsystems which form a data base that can be customized for any machine shop. (Fig. l.) The first subsystem defines the part model based on the completed part design, specification input, and raw material description. The user has the option of entering the part data interactively or in batch mode. The second subsystem defines the manufacturing logic based on user input of such items as the order and purpose of the operations. The third subsystem, for defining manufacturing resources, establishes information about shop facilities and shop rules and procedures. The final subsystem creates and displays the process plan. [Pg.156]


See other pages where Second Order Complete Plan is mentioned: [Pg.395]    [Pg.395]    [Pg.396]    [Pg.568]    [Pg.558]    [Pg.257]    [Pg.424]    [Pg.70]    [Pg.178]    [Pg.654]    [Pg.1197]    [Pg.342]    [Pg.25]    [Pg.18]    [Pg.93]    [Pg.34]    [Pg.2045]    [Pg.156]    [Pg.961]    [Pg.11]    [Pg.4]    [Pg.114]    [Pg.1095]    [Pg.544]    [Pg.147]    [Pg.200]    [Pg.14]   


SEARCH



Planned orders

© 2024 chempedia.info