Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Placement drills

Placement drills. These machines can place the fertiliser in bands 5-7 cm to the side and 3-5 cm below the row of seeds. It is more efficient than broadcasting for crops such as peas and sugar beet. Other types of placement drills attached... [Pg.81]

Primary production typically recovers 10—25% of the oil originally ia the reservoir. Efficiency of primary production is related to oil properties, reservoir properties, geometric placement of oil wells, and the drilling and completion technology used to drill the wells and prepare them for production. Pumping the well can maintain production at economic levels for years. [Pg.188]

Maxiniizing the lvalue of the reservoir requires that full reservoir dynamics be considered in drilling wells and in extracting oil. Gas and water must be recycled through the strategic placement of injection wells wells with high gas-oil or water-oil ratios must be closed or not drilled and the rate of oil production must be controlled to maintain underground pressure. [Pg.961]

Figure 4-162 shows a natural diamond drill bit which has a long outer taper and medium inner cone, radial flow fluid courses, and five to six stones per carat (spc) diamonds set with a medium placement density. Using the definitions in Figures 4-156, 4-158, 4-159, and 4-160, the characteristics of this bit are coded D 2 R 5 as follows ... [Pg.806]

If a well proves productive, the ensuing completion operation may require an area in excess of the drilling area. This may mean allocations for frac tank placement, blenders, pump trucks, bulk trucks and nitrogen trucks. In today s economic climate, the operator should weigh the probability of success, Bayes theorem (Equation 4-373), with the cost of constructing and reclaiming an additional area needed for stimulation (Equation 4-374). Plans such as these... [Pg.1350]

A commonly employed method to minimise ohmic potential drop effects is to place the reference electrode very close to the working electrode by means of a Luggin capillary. The disadvantage of very close placement, which may be unacceptable, is disturbance of the fluid flow. To avoid this, other methods are sometimes used. For example, a rotating disc electrode has been described in which the reference electrode is placed in a tiny compartment within the rotating electrode assembly and linked to the solution via a tiny orifice (0.7 mm) drilled in the centre of the disc [88]. [Pg.386]

One possible marking system which has such features has been developed at this Institute (20). This marking system is based on the drilling of an array o7 holes into the item an encoding system is utilized such that the serial number is represented by the relative placement of the holes. [Pg.68]

The application of simulation to a disaster event can be as simple as using the simulators to drill evacuation procedures at a long-term care (ETC) facility. With hurricane season on us, several ETC organizations will begin to work with their staff to do just that. By programming the simulators to be elderly with chronic conditions and adding a nasal O2 mask, staff will be able to evaluate the effectiveness of their evacuation plan. Or perhaps the placement of patient simulators within a hospital itself... [Pg.599]

Because the type of initiator/detonator is left up to the builder,you will also have to choose the appropriate type of trigger and safety. Once these are installed, the front grip may be epoxied or screwed in place between the side pieces A.It may be necessary to drill linkage holes through the grip,so screw placement should be decided after this has been done... [Pg.141]

Tap the four holes just drilled in the blind flanges for 34" NPT thread. Do not tap the thread all the way through the flanges. Tap each flange from the flat side, which will be the outside when electrolyzer is constructed. The flange faces that will be inside have a raised surface for gasket placement. [Pg.128]

It was a small but important step to advance from opportunistic oil recovery from surface seeps to the placement of wells in or near these surface deposits to try to increase production. Probably the first wells in the Western world for oil recovery were drilled during the period 1785-1849 in the Pechelbronn area of France [4]. None of these wells, which ranged in depth from 31 to 72 m, was a prolific producer but they did establish the practice of drilling for oil in Europe. [Pg.557]

Soil nailing is similar to ground anchors or tiebacks in that a steel rod is grouted into a pre-drilled hole. There are, however, several important differences. Nails are considerably smaller and shorter than anchors, and while anchors are pre-stressed after placement, nails are not (with few exceptions in which a very small pre-stress is applied), and do not pick up load until the soil mass deforms. Nails, like anchors, add shear resistance to the soil mass. [Pg.107]

There are three jet grouting systems in common use. These are the single jet or monofluid system, the two fluid, and the three fluid systems. All systems require the placement of the jet pipe to the bottom of the depth to be treated. This is done using conventional drilling methods appropriate for the soil being treated. Depths of 150 feet have been successfully treated, and greater depths are possible under certain conditions. Any soil in which the jet pipe can be placed can be successfully treated. Adverse condition include soil deposits which contain large amounts of boulders. [Pg.136]

Drilling Holes I Placement of Packers—One-inch holes were drilled in the vicinity of the leaks to the point of intersection of the construction joints, 8 to 10 inches from the surface. An electric handheld diamond coring drill was used. Next, packers were inserted in the holes and tightened to provide a pressure-tight seal. [Pg.340]

The first one has to do with the setting of the cement slurry that is accelerated by an increase of the temperature (and also of the pressure to a lesser extent). It is obviously important that the cement slurry remains liquid during the placement period. But once in place it must set within a reasonable amount of time for the next operations to be performed as soon as possible (further drilling, well completion, and so on). [Pg.605]

The pre-placement stage started immediately after the borehole had been drilled. During this stage, instrumentation was installed in the borehole to measure the rate of seepage from the saturated rock into the empty borehole. [Pg.466]

From December 1968 on at Experimental Section I, and from March 1970 on at Experimental Section II, the density of airflow declined to the minimum values, at which the process of in situ combustion begins to fade out. At the same time, the effectiveness of oil displacement also started to diminish. The increase in the additional oil produced during the subsequent two years, in 1973 and 1974, was due to placement in production of five new wells drilled during 1972. The operating conditions of production wells were also improved, at that time, when the entry of sand into the wells was finally stopped by coking of these sands in the bottomhole zones. [Pg.161]


See other pages where Placement drills is mentioned: [Pg.13]    [Pg.366]    [Pg.379]    [Pg.813]    [Pg.849]    [Pg.1353]    [Pg.293]    [Pg.794]    [Pg.28]    [Pg.212]    [Pg.222]    [Pg.151]    [Pg.505]    [Pg.75]    [Pg.280]    [Pg.129]    [Pg.287]    [Pg.504]    [Pg.13]    [Pg.47]    [Pg.505]    [Pg.1583]    [Pg.582]    [Pg.458]    [Pg.419]    [Pg.167]    [Pg.13]    [Pg.426]    [Pg.601]    [Pg.603]    [Pg.175]    [Pg.577]   


SEARCH



Placement

© 2024 chempedia.info