Schedule master project

Business Planning/Project Development Initial Involvement/PIan of Action Process Design Estimating Project Execution Plan/Master Project Schedule Engineer, Procure, Construct... [Pg.5]

Project Execution Plan/Master Project Schedule... [Pg.8]

PROJECT EXECUTION PLAN/ MASTER PROJECT SCHEDULE... [Pg.85]

General Preliminary Execution Plan Validity Check Project Specific Durations Questions/Decisions Master Project Schedule Firm Execution Plan Presentation Compressing the Schedule Project Coordination Procedure... [Pg.85]

Trying to execute a project without an execution plan and a master project schedule (MPS) is like trying to drive from here to there without a map or a elock. Eventually you will get nowhere, you will be late getting there, and you won t even know it. A project execution plan combined with the MPS provides a road map with criteria to judge where you are at any time and to know when you have arrived. It also provides the basis for the control system and is an excellent communication tool. [Pg.85]

It must be noted that while a schedule is a stand-alone document, the execution plan could not exist without the master project schedule. [Pg.87]

The appropriation estimate and the master project schedule are available. [Pg.89]

The master project schedule (MPS), like the appropriation estimate, is a standalone document that must be completed before a firm execution plan can be... [Pg.96]

Prepare a realistic master project schedule and firm execution plan to support the appropriation estimate (Chapters 8 and 10). [Pg.201]

The project execution plan and master project schedule developed by the Owner s Project Manager during the initial project stages (Chapter 9) set the basis and execution logic for the entire project and, normally, are all that is needed to execute small projects. However, in major projects, the responsibility for the actual execution is eventually turned over to an EPC contractor who must assume the planning and scheduling functions and issue an expanded execution plan and MPS in details commensurate with the size and complexity of the project. [Pg.227]

Correction The Construction Manager must insist that every subcontractor submit its own labor-loaded schedule and check them for compatibility with each other and with the master project schedule. [Pg.231]

Most owners require that AFE s (authorizations for expenditure) for important projeets be aecompanied by at least a preliminary quality estimate and a Master Project Schedule (MPS) with a firm projeet exeeution plan. These should always... [Pg.371]

The activities breakdown parallels the preliminary semi-detailed cost estimate in Appendix L and the Master Project Schedule illustrated in Appendix E. [Pg.395]

Execution Plan/Master Project Schedule for Case Study (Appendix E.)... [Pg.487]


See other pages where Schedule master project is mentioned: [Pg.96]    [Pg.351]    [Pg.372]    [Pg.376]   