Communicate and Get Approval of the Plan

Piiot Testing. Pilot testing of each PSM system will be performed at two locations to be selected by the project team. The test period will be two months. During the test period, the project team will monitor the PSM system to assure that procedures are clear and do not conflict with other procedures. [Pg.121]

Training. The project team will define the training needed for implementation of each new PSM system. The amount and type of training, and the number of staff requiring training, will be identified in the procedure developed. [Pg.121]

Installation. Installation of each new PSM system will occur after the pilot test phase. Documentation on the procedure will be circulated, and the procedure will be described at a meeting of the company Engineering Council. [Pg.121]

Verification. Each PSM system will include a mechanism for verifying installation. This will either be the requirement for copies of documentation being sent to Corporate EHS, or another mechanism defined by the project team. [Pg.121]

FIGURE 5-13. Example of Project Plan Sections on Installation and Verification and Financial Controls  [Pg.121]


See other pages where Communicate and Get Approval of the Plan is mentioned: [Pg.121]    [Pg.121]    [Pg.123]   