Basis for the flow-sheet calculations

Basis for the flow-sheet calculations Time basis [Pg.142]

No plant will operate continuously without shut-down. Planned shut-down periods will be necessary for maintenance, inspection, equipment cleaning, and the renewal of catalysts [Pg.142]

It is usually easiest to carry out the sequence of flow-sheet calculations in the same order as the process steps starting with the raw-material feeds and progressing stage by stage, where possible, through the process to the final product flow. The required production rate will usually be specified in terms of the product, not the raw-material feeds, so it will be necessary to select an arbitrary basis for the calculations, say 100 kmol/h of the principal raw material. The actual flows required can then be calculated by multiplying each flow by a scaling factor determined from the actual production rate required. [Pg.143]




SEARCH



Basis for

Basis for calculations

Calculation sheets

Calculations, basis

Flow calculation

Flow sheets

Flow-sheet calculations

Flow-sheeting

© 2024 chempedia.info