Resolving PSSR Issues and Action Items

An overall review of the management of change documentation package should be performed to ensure documentation update items (including material safety data sheets) are addressed and that PHA action items are complete. This can be done by one person but is often best achieved by a PSSR Team. The process needs to account for  [Pg.98]

It is necessary for the PSSR team to perform a detailed physical inspection of the new or changed process. This can help find items like physical obstructions, potential for unintended mixing, siphoning, and other issues prior to the testing phase. [Pg.98]