Updating the schedule to account for actual process information [Pg.228]

Many plant schedulers use spreadsheets to aid with these tasks, but spreadsheets can be difficult to update and maintain, and they cannot comprehensively account for complex dependencies. Recipe-based scheduling tools greatly reduce the effort required for managing plants on a day-to-day basis. [Pg.228]

Let s assume that the polymerization reaction in batch BB-1-3 (the third batch of the first BB campaign that utihzes R-1) took 4 h longer than plaimed. As a result, the end of batch BB-1-3 in reactor R-1 has a conflict with the scheduled staxt time of batch AA-2-2 that was scheduled to utilize the same reactor. This conflict is displayed in Figme 15.18 with a new line on the equipment occupancy chart directly below line R-1 (this new hne is labeled with an exclamation point and the conflicting procedure associated with batch AA-2-2 is outhned in red). Furthermore, the delay in the polymerization operation in batch BB-1-3 has delayed subsequent operations [Pg.228]


See other pages where Labor demand chart is mentioned: [Pg.228]    [Pg.228]    [Pg.860]    [Pg.684]    [Pg.279]    [Pg.864]   


SEARCH



Labor

Laborant

© 2024 chempedia.info