Big Chemical Encyclopedia

Chemical substances, components, reactions, process design ...

Articles Figures Tables About

Daywork sheets

The time spent on each job and the materials used are sometimes recorded on the job sheet, but alternatively a daywork sheet can be used. This will depend upon what is normal practice for the particular electrical company. This information can then be used to bill the customer for work carried out. [Pg.344]

Daywork is one way of recording variations to a contract, that is, work done which is outside the scope of the original contract. If daywork is to be carried out, the site supervisor must first obtain a signature from the client s representative, for example, the architect, to authorize the extra work. A careful record must then be kept on the daywork sheets of all extra time and materials used so that the client can be billed for the extra work. A typical daywork sheet is shown in Fig. 5.13. [Pg.344]

Figure 5.13 Typical daywork sheet or variation order,... Figure 5.13 Typical daywork sheet or variation order,...
Briefly state why we would use a daywork sheet to record additional work... [Pg.201]


See other pages where Daywork sheets is mentioned: [Pg.344]    [Pg.345]    [Pg.351]    [Pg.351]    [Pg.351]    [Pg.351]    [Pg.198]    [Pg.199]    [Pg.199]    [Pg.201]    [Pg.201]    [Pg.201]    [Pg.201]    [Pg.372]    [Pg.373]    [Pg.390]    [Pg.390]    [Pg.390]    [Pg.390]    [Pg.3930]   
See also in sourсe #XX -- [ Pg.187 ]




SEARCH



© 2024 chempedia.info