Transfer of Care, Custody, and Control

At the conclusion of Phase IV, the facility wiU be handed over to the owner/operator through the use of Turnover Packages, as described later. This activity is sometimes referred to as Transfer of Care, Custody, and Control (TCCC). This is a very important time in the project because control of the facility now resides with the operator, not the contractor. This means that the operator s safety systems now become operative. Therefore, if the contractor wishes to change anything he or she has to work through the operator s Management of Change process. [Pg.709]